Project Details Report Annual Trail Reconstruction Project Name Annual Trail Reconstruction Project # PA-27-01
Total Project Cost $514,500
Public Works Director
Contact
Park Asset Internal Serv. Fund
Improvement 2 - Smart to do
Department
Type
Park Improvements
Category
Priority
Active
15 years
Status
Useful Life
Park Asset IS Fund
Fund
Description
This project includes the rehabilitation of existing bituminous trails in the city, that serve parks or as regional trail systems.
* 2027 - Includes segments within Prairie Bend Park and Scenic Heights Parks
Justification Ongoing maintenance of recreation trails as part of an overall pavement management program. The trails pavement condition has deteriorated as it nears life expectancy. Upgrade all trails old and new to meet ADA specifications
Expenditures
2027
2028
2029
2030
2031
Total
Construction/Maintenance
139,000
76,000 10,000
78,500 10,000
80,000 10,000
82,000 10,000
455,500
Engineering/Administration
19,000
59,000
158,000
86,000
88,500
90,000
92,000
514,500
Total
Funding Sources
2027
2028
2029
2030
2031
Total
Park Asset Internal Service Fund
158,000
86,000
88,500
90,000
92,000
514,500
158,000
86,000
88,500
90,000
92,000
514,500
Total
Budget Impact The City must reconstruct pedestrian ramp facilities to comply with its ADA Transition plan adopted in 2018, increasing the cost of future trail projects compared to previous years' projects