2027-31 Capital Improvement Plan
O'Dowd Parking Lot and Park Rehab Project Name O'Dowd Parking Lot and Park Rehab Project # PA-31-06
Total Project Cost $366,000
Director of Planning & Development
Contact
Park Asset Internal Serv. Fund
Improvement 3 - Want to do
Department
Type
Park Improvements
Category
Priority
Active
30 years
Status
Useful Life
Park Development Fund
Fund
Description
Upgrade the gravel parking lot to bituminous, reconstruct ADA compliant trail, replace dock, replace retaining walls and other park amenities.
Justification
By upgrading the lot, this will help with ADA parking lot requirements which will provide easier access to trails for individuals with accessibility issues. The existing trail is non-ADA compliant. The existing infrastructure is at the end of its useful life.
Expenditures
2027
2028
2029
2030
2031
Total
Construction/Maintenance
0 0 0
0 0 0
0 0 0
0 0 0
250,000 61,000 55,000
250,000
Improvements
61,000
Engineering/Administration
55,000
0
0
0
0
366,000
366,000
Total
Funding Sources
2027
2028
2029
2030
2031
Total
Park Asset Internal Service Fund
0
0
0
0
366,000
366,000
0
0
0
0
366,000
366,000
Total