2027-31 Capital Improvement Plan
Computer Replacements Project Name Computer Replacements Project # IT-002
Total Project Cost $560,000
I.T. Director Equipment
Contact
I.T. Internal Service Fund
Department
Type
IT Infrastructure
2 - Smart to do
Category
Priority
Active
4 years
Status
Useful Life
I.T. Internal Service Fund
Fund
Description Scheduled replacement of employee workstations. Each year a planned segment of employees receives a replacement computer if their device reaches its 4-5 year life expectancy depending on the device and its overall use.
Justification Employee workstations, laptops, and tablets are on a 4-5 year replacement cycle. Devices are purchased with a 4 year warranty to reduce additional costs during the life of the device. Hardware failures and reduced performance of these devices is alleviated with purchasing new technology at the 4-5 year mark. A portion of older computers past the 4-5 year mark are used for summer interns, contractors, or areas that infrequent computer use is required to help reduce overall costs.
Expenditures
2027
2028
2029
2030
2031
Total
Equip/Vehicles/Furnishings
100,000
100,000
120,000
120,000
120,000
560,000
100,000
100,000
120,000
120,000
120,000
560,000
Total
Funding Sources
2027
2028
2029
2030
2031
Total
I.T. Internal Service Fund
100,000
100,000
120,000
120,000
120,000
560,000
100,000
100,000
120,000
120,000
120,000
560,000
Total
Budget Impact Computer replacement costs are factored into the IT Internal Fund budget process.