2027-31 Capital Improvement Plan
Community Center Rooftop Unit Project Name Community Center Rooftop Unit Project # BA-27-003
Total Project Cost $30,000
Assistant City Administrator
Contact
Building Internal Service Fund
Community Center
Department
Type
Recreation
1 - Have to do
Category
Priority
Active
15 years
Status
Useful Life
Building Asset IS Fund
Fund
Description Replacement of an HVAC rooftop unit at the Community Center.
Justification There are 12 total rooftop units at the Community Center, and they will all be reaching the end of their useful life. Replacement of these units will decrease long-term maintenance costs and improve energy efficiency.
Expenditures
2027
2028
2029
2030
2031
Total
Equip/Vehicles/Furnishings
30,000
0
0
0
0
30,000
30,000
0
0
0
0
30,000
Total
Funding Sources
2027
2028
2029
2030
2031
Total
Building Internal Service Fund
30,000
0
0
0
0
30,000
30,000
0
0
0
0
30,000
Total
Produced Using Plan-It CIP Software
174
Made with FlippingBook flipbook maker