2027-31 Capital Improvement Plan
Community Center HVAC Rooftop Unit Project Name Community Center HVAC Rooftop Unit Project # BA-28-002
Total Project Cost $50,000
Assistant City Administrator
Contact
Building Internal Service Fund
Buildings
Department
Type
Recreation
1 - Have to do
Category
Priority
Active
20 years
Status
Useful Life
Building Asset IS Fund
Fund
Description Replacement of a rooftop unit at the Community Center.
Justification
The rooftop HVAC unit at the Community Center will have reached the end of its useful life. Timely replacement is necessary to avoid a lapse in HVAC service at the facility.
Expenditures
2027
2028
2029
2030
2031
Total
Construction/Maintenance
0
50,000
0
0
0
50,000
0
50,000
0
0
0
50,000
Total
Funding Sources
2027
2028
2029
2030
2031
Total
Building Internal Service Fund
0
50,000
0
0
0
50,000
0
50,000
0
0
0
50,000
Total
Produced Using Plan-It CIP Software