Annual Erosion/Pond Cleaning/Outlet Improvements Project Name Annual Erosion/Pond Cleaning/Outlet Improvements Project # Storm-27-001

Total Project Cost $1,000,000

City Engineer Maintenance 2 - Smart to do

Contact

Storm Drainage Fund Storm Sewer/Drainage

Department

Type

Category

Priority

Active

Surface Water Fund

Status

Fund

Description This project is a placeholder for improvements in future years to address erosion and pond maintenance issues.

Justification These projects are needed to address safety, erosion, water quality and pond outlet issues when large maintenance or repairs are needed.

Expenditures

2027

2028

2029

2030

2031

Total

Construction/Maintenance

175,000

175,000

175,000

175,000

175,000

875,000

Engineering/Administration

25,000

25,000

25,000

25,000

25,000

125,000

200,000

200,000

200,000

200,000

200,000

1,000,000

Total

Funding Sources

2027

2028

2029

2030

2031

Total

Storm Drainage Fund

200,000

200,000

200,000

200,000

200,000

1,000,000

200,000

200,000

200,000

200,000

200,000

1,000,000

Total

Budget Impact

Projects are identified through issues with frequent maintenance, and inspections required by the NPDES MS4 permit. Pond cleanouts may also be identified adjacent to road maintenance and construction projects.

Produced Using Plan-It CIP Software