2027-31 Capital Improvement Plan

City of Shakopee 15-YR Capital Improvement Plan (2027-2041) FINAL October 23, 2026

Large City

Project Number

(CIF) Capital

Grant Funding

Special

Assistance and

SPUC Sanitary Sewer Storm Drainage

Park

Park Asset

Building Internal

EDA

Total Project

Project

Improvement Fund

Assessments

MSA Fund

(Watermain)

Fund

Fund

Development

Fund

Service Fund Revenue Fund

Cost

NOTES

2036

Annual Pavement Rehabilitation Annual Bituminous Mill and Overlay Annual Trail Rehabilitation (along roadways) 2036 Full Depth Pavement Reconstruction 2037 Full Depth Pavement Reconstruction Annual Pavement Reclamite

CIF-36-TBD CIF-36-TBD CIF-36-TBD CIF-36-TBD CIF-36-TBD CIF-37-TBD

$300,000 $4,235,000 $180,000 $150,000 $3,090,000 $300,000

$300,000 $5,450,000 $180,000 $150,000 $4,350,000 $300,000

$1,100,000

$25,000

$30,000

$60,000

$1,140,000

$0

$30,000

$30,000

$60,000

Trunk Sewer Extensions

Sewer-36-001

$217,000

$217,000

Annual Native Vegetation Management Annual Erosion/Pond Cleaning/Outlet Imp Annual Drainage and Flood Prevention Imp Public Works Surface Water: Skidsteer Loader

Storm-36-TBD Storm-36-TBD Storm-36-TBD Storm-36-TBD Storm-36-TBD

$125,000 $200,000 $120,000 $12,700 $14,800

$125,000 $200,000 $120,000 $12,700 $14,800 $101,000 $24,000 $120,000 $180,000 $60,000 $180,000 $29,000 $80,000 $110,000 $240,000 $20,000 $17,000 $17,000

Public Works Surface Water: UTV

Annual Trail Reconstruction Annual Fence Replacement Annual Parking Lot Rehabilitation

PA-36-01 PA-36-02 PA-36-TBD PA-36-TBD PA-36-TBD PA-36-TBD BA-36-001 BA-36-TBD BA-36-TBD BA-36-TBD BA-36-TBD BA-36-TBD

$101,000 $24,000 $120,000 $180,000 $60,000 $180,000 $29,000

Annual Playground Equipment and ADA Improvements PA-36-TBD

Annual Playground Court Resurfacing Green Meadows Plaground and Furnishings Lions Park Rhapsody Music Equipment

Misc Building Improvements Fire Station #1 Boilers Fire Station #2 Rooftop Units 500 Gorman Bldg. Water Softener 500 Gorman Bldg. Rooftop Unit

$80,000 $110,000 $240,000 $20,000 $17,000 $17,000

Library Water Heater

$12,597,500

2036 Subtotal

$8,255,000

$0

$1,140,000

$1,100,000 $4,022,032 $2,922,032

$55,000

$277,000

$592,500

$0

$694,000

$484,000

$0

1/1/36 Balance Avail

12/31/36 Balance Remaing

2037

Annual Pavement Rehabilitation

CIF-37-TBD CIF-37-TBD CIF-37-TBD CIF-37-TBD CIF-38-TBD

$300,000 $190,000 $345,000 $4,495,000 $350,000

$300,000 $190,000 $345,000 $9,610,000 $350,000

Annual Trail Rehabilitation (along roadways)

Annual Pavement Reclamite

2037 Full Depth Pavement Reconstruction 2038 Full Depth Pavement Reconstruction

$2,350,000

$2,500,000

$65,000

$65,000

$135,000

Trunk Sewer Extensions Jetter Truck (Freightliner)

Sewer-37-00=1 Sewer-37-TBD Storm-37-TBD Storm-37-TBD Storm-37-TBD Storm-37-TBD Storm-37-TBD Storm-37-TBD

$221,000 $626,000

$221,000 $626,000 $125,000 $200,000 $122,000 $26,900 $13,000 $133,000 $103,000 $25,000 $122,000 $183,000 $61,000

Annual Native Vegetation Management Annual Erosion/Pond Cleaning/Outlet Imp Annual Drainage and Flood Prevention Imp Public Works Surface Water: Skidsteer Loader Public Works Surface Water: Tractor 3 Point Front PTO

$125,000 $200,000 $122,000 $26,900 $13,000 $133,000

Annual Trail Reconstruction Annual Fence Replacement Annual Parking Lot Rehabilitation

PA-37-01 PA-37-02 PA-37-TBD

$103,000 $25,000 $122,000 $183,000 $61,000

Annual Playground Equipment and ADA Improvements PA-37-TBD

Annual Playground Court Resurfacing

PA-37-TBD

Misc Building Improvements

BA-37-001

$80,000

$80,000

$12,835,900

2037 Subtotal

$5,680,000

$0

$2,350,000

$2,500,000 $5,862,032 $3,362,032

$65,000

$912,000

$754,900

$0

$494,000

$80,000

$0

1/1/37 Balance Avail

12/31/37 Balance Remaing

Page 9 of 11

260

Made with FlippingBook flipbook maker