2027-31 Capital Improvement Plan

2027 Full-Depth Pavement Reconstruction Project Name 2027 Full-Depth Pavement Reconstruction Project # CIF-27-001

Total Project Cost $5,050,000

City Engineer Improvement 1 - Have to do

Contact

Capital Improvements Fund

Department

Type

Street Reconstruction

Category

Priority

Active

30 years

Status

Useful Life

Capital Improvement Fund

Fund

Description

This project is for the full depth reconstruction of the bituminous roadway for Shenandoah Drive from 4th Ave to Unbridled Ave, Vierling Drive from Ramsey St to Eagle Creek Blvd, and portions of Pierce Street, McDevitt St, Shumway Street, Thomas Avenue, Hennes Avenue, Menke Circle and Menke Avenue. Additional storm sewer improvements, as well as utility and curb and gutter repairs and improvements will be evaluated and included with this project.

Justification This is a continuation of the City's Pavement Preservation Program to maintain existing infrastructure.

Prior

Expenditures

2027

2028

2029

2030

2031

Total

0

Construction/Maintenance

4,600,000

0 0

0 0

0 0

0 0

4,600,000

Engineering/Administration

450,000

450,000

5,050,000

0

0

0

0

5,050,000

Total

Prior

Funding Sources

2027

2028

2029

2030

2031

Total

0

Capital Improvement Fund

4,080,000

0 0 0 0 0

0 0 0 0 0

0 0 0 0 0

0 0 0 0 0

4,080,000

Special Assessments

770,000 90,000 60,000 50,000

770,000

Storm Drainage Fund

90,000

Sanitary Sewer Fund

60,000

Cost Sharing, SPUC

50,000

5,050,000

0

0

0

0

5,050,000

Total

Budget Impact

The reconstruction of roadways is necessary to replace the complete pavement section after they have degraded beyond the point where maintenance such as overlays, potholes repair and patching is effective.