2027-31 Capital Improvement Plan
2028 Full-Depth Pavement Reconstruction Project Name 2028 Full-Depth Pavement Reconstruction Project # CIF-28-001
Total Project Cost $5,350,000
City Engineer Improvement 1 - Have to do
Contact
Capital Improvements Fund
Department
Type
Street Reconstruction
Category
Priority
Active
30 years
Status
Useful Life
Capital Improvement Fund
Fund
Description
This project is for the full depth reconstruction of the bituminous roadway for 10th Avenue from Harrison Street to Apgar Street. As part of this project, a reduction from a 4-lane section to a 3-lane section and pedestrian improvements will be considered. The City will be applying for Safe Routes to School and Regional Solicitation funds to include the multi-modal improvements with the project. Additional storm sewer improvements as well as utility and curb and gutter repairs and improvements will be evaluated and included with this project.
The project also includes full-depth reconstruction of Valley View Road from 17th Avenue to Countryside Drive.
Funding for 10th Avenue is programmed in 2026 to prepare grant applications and complete preliminary engineering to determine the appropriate multi-modal improvements.
Justification This is a continuation of the City's Pavement Preservation Program to maintain existing infrastructure.
Prior
Expenditures
2027
2028
2029
2030
2031
Total
0
Construction/Maintenance
0
4,600,000
0 0
0 0
0 0
4,600,000
Engineering/Administration
350,000
400,000
750,000
350,000
5,000,000
0
0
0
5,350,000
Total
Prior
Funding Sources
2027
2028
2029
2030
2031
Total
0
MSA - State Aid
0
2,800,000 1,720,000
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
2,800,000
Capital Improvement Fund
350,000
2,070,000
Special Assessments
0 0 0 0
315,000 120,000 30,000 15,000
315,000
Storm Drainage Fund
120,000
Cost Sharing, SPUC
30,000
Sanitary Sewer Fund
15,000
350,000
5,000,000
0
0
0
5,350,000
Total
Budget Impact
The reconstruction of roadways is necessary to replace the complete pavement section after they have degraded beyond the point where maintenance such as overlays, potholes repair and patching is effective.
Produced Using Plan-It CIP Software