2027-31 Capital Improvement Plan
2030 Full-Depth Pavement Reconstruction Project Name 2030 Full-Depth Pavement Reconstruction Project # CIF-30-001
Total Project Cost $7,400,000
City Engineer Improvement 1 - Have to do
Contact
Capital Improvements Fund
Department
Type
Street Reconstruction
Category
Priority
Active
30 years
Status
Useful Life
Capital Improvement Fund
Fund
Description
This project is for the full depth reconstruction of the bituminous roadway for 11th Avenue, Polk St S, 13th Avenue, Taylor St S, Tyler St S, Harrison St S, Presidential Lane, Presidential Circle, Monroe St S, Jefferson St S, Madison St S,
Justification This is a continuation of the City's Pavement Preservation Program to maintain existing infrastructure.
Prior
Expenditures
2027
2028
2029
2030
2031
Total
0
Construction/Maintenance
0 0
0 0
0
6,400,000
0 0
6,400,000
Engineering/Administration
450,000
550,000
1,000,000
0
0
450,000
6,950,000
0
7,400,000
Total
Prior
Funding Sources
2027
2028
2029
2030
2031
Total
0
Capital Improvement Fund
0 0 0 0 0 0
0 0 0 0 0 0
450,000
4,563,000 2,000,000
0 0 0 0 0 0
5,013,000
Special Assessments
0 0 0 0 0
2,000,000
Storm Drainage Fund
150,000 127,000 60,000 50,000
150,000
MSA - State Aid
127,000
Cost Sharing, SPUC
60,000
Sanitary Sewer Fund
50,000
0
0
450,000
6,950,000
0
7,400,000
Total
Budget Impact
The reconstruction of roadways is necessary to replace the complete pavement section after they have degraded beyond the point where maintenance such as overlays, potholes repair and patching is effective.