B. Association for the Advancement of Cost Engineering Classifications The five estimate classes in the AACE Cost Estimation Classification Matrix are determined by level of ‘project definition’ with consideration to a set of secondary characteristics.

1

2

Primary Characteristic

Secondary Characteristic

Level of Project Definition (expressed as % of complete definition)

Expected Accuracy Range Typical Variation in Low and High Range

3

End Usage Typical Purpose of Estimate

Methodology Typical Estimating Method

Estimate Class

Capacity factored, parametric models, judgement or analogy Equipment factored or parametric models Semi-detailed unit costs with assembly level line items Detailed unit costs with forced detailed take off Detailed unit cost with detailed take off

4

L: -20% to -50% H: +30% to +100%

Class 5

0% to 2%

Concept screening

L: -15% to -30% H: +20% to +50%

5

Class 4

1% to 5%

Study or feasibility

L: -10% to -20% H: +10% to +30%

Budget authorisation or control

Class 3

10% to 40%

6

Control or bid/tender

L: -5% to -15% H: +5% to +20%

Class 2

30% to 70%

7

L: -3% to -10% H: +3% to +15%

Check estimate or bid/tender

Class 1

50% to 100%

8

9

page 53