B. Association for the Advancement of Cost Engineering Classifications The five estimate classes in the AACE Cost Estimation Classification Matrix are determined by level of ‘project definition’ with consideration to a set of secondary characteristics.
1
2
Primary Characteristic
Secondary Characteristic
Level of Project Definition (expressed as % of complete definition)
Expected Accuracy Range Typical Variation in Low and High Range
3
End Usage Typical Purpose of Estimate
Methodology Typical Estimating Method
Estimate Class
Capacity factored, parametric models, judgement or analogy Equipment factored or parametric models Semi-detailed unit costs with assembly level line items Detailed unit costs with forced detailed take off Detailed unit cost with detailed take off
4
L: -20% to -50% H: +30% to +100%
Class 5
0% to 2%
Concept screening
L: -15% to -30% H: +20% to +50%
5
Class 4
1% to 5%
Study or feasibility
L: -10% to -20% H: +10% to +30%
Budget authorisation or control
Class 3
10% to 40%
6
Control or bid/tender
L: -5% to -15% H: +5% to +20%
Class 2
30% to 70%
7
L: -3% to -10% H: +3% to +15%
Check estimate or bid/tender
Class 1
50% to 100%
8
9