Task Description (NS)

BPMilestone (written key)

Permit issued, structurals selected

1

Start Pack Received

Start Pack Received

Pool Stakeout

Pool Stakeout

Pool Dig

Pool Dig/Form/Steel

Pool Gunite

Pool Gunite

Lot Grubbed/Balanced

Homesite Clear/Balance Lot Grubbed/Balanced Pre-Construction Meeting Survey Pinning/Stakeout

Lot Grubbed/Balanced

Pre-Construction Meeting

Stakeout

JBST (Dig Footers/Formboards)

Dig Footers/Formboards/Foundation [JBST]

Footer Steel

Footer Steel

Form Basement Walls

Form Basement Walls Basement Walls Poured Waterproof Basement Basement Walls Framed Underground Plumbing HVAC Underground Electric Underground

Basement Walls Poured

Waterproof Basement

Basement Walls Framed

Install Foundation Masonry Piers

Install Foundation Masonry Piers

Plumbing Underground

HVAC Underground

Electric Underground

Slab Steel Prep

Slab Steel Prep

Stem Wall Complete

Stem Wall Complete

Foundation Pour

2

Foundation Pour

Deliver Framing/Rough Lumber

Deliver Framing/Rough Lumber Foundation Floor Framing Complete

Foundation Floor Framing Complete

Stucco Grade Complete

Stucco Grade Complete

1st Flr Block/Framing Complete

1st Flr Block/Framing Complete Prep/Steel 1st Floor Beam

Prep/Steel 1st Floor Beam

Pour 1st Floor Beam

Pour 1st Floor Beam Floor Trusses Installed 2nd Floor Deck Complete 1st Floor Stairs Installed

Floor Trusses Installed

2nd Floor Deck Complete

1st Floor Stairs Installed

Stairs Installed

Stairs Installed

2nd Flr Block/Framing Complete

2nd Flr Block/Framing Complete Prep/Steel 2nd Floor Beam

Prep/Steel 2nd Floor Beam

Pour 2nd Floor Beam

Pour 2nd Floor Beam

Wall Sheathing

Wall Sheathing

Floor Trusses Installed - 3rd Floor

Floor Trusses Installed - 3rd Floor

3rd Floor Deck Complete

3rd Floor Deck Complete