FY 2018-19 and 2019-20 Adopted Operating and CIP Budget

CITY OF MORGAN HILL CAPITAL IMPROVEMENT PROGRAM

Strategic Planning Documents Bikeways, Trails, Parks and Recreation Master Plan

Expenditure Schedule & Category

Parks & Recreation: 110097

2018-19

2019-20

2020-21

2021-22

2022-23

2023-24

86120 - Property Acquisition

$70,000

$70,000

$70,000

$70,000

$2,070,000

$70,000

PROJECT COST

$70,000

$70,000

$70,000

$70,000

$2,070,000

$70,000

Funding Source(s)

2018-19

2019-20

2020-21

2021-22

2022-23

2023-24

f301 - Park Impact Fund

$70,000

$70,000

$70,000

$70,000

$2,070,000

$70,000

FUNDING TOTALS

$70,000

$70,000

$70,000

$70,000

$2,070,000

$70,000

Financial Comments This project pays approximately $70,000 in property taxes annually for land banked park property in the County.

Estimated Project Schedule

Timeframe

Planning

Ongoing

Right-of-Way Acquisition & Permitting

Next park acquisition is planned for FY 2022-23

Operating Cost Impacts No new operational costs are incurred prior to development if other alternate uses, such as farming, can be identified. Without an alternate use, annual cost to abate weeds would be approximately $125 per acre. Property land banked in the County for future City use requires payment of property taxes. New park development will require additional funds for maintenance. New funding levels will be dependent on the size and amenities developed within each park.