FY 2018-19 and 2019-20 Adopted Operating and CIP Budget
CITY OF MORGAN HILL CAPITAL IMPROVEMENT PROGRAM
Expenditure Schedule & Category
Parks & Recreation:
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
86201 - Environmental Clearances
$10,000
86220 - Architecture and Design
$60,000
$22,400
86360 - Construction
$824,000
86530 - Project Implementation
$41,000
$41,000
PROJECT COST
$111,000
$887,400
Funding Source(s)
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
f301 - Park Impact Fund
$111,000
$887,400
FUNDING TOTALS
$111,000
$887,400
Financial Comments For the total project, $229,500 is being sought from a State grant, $200,000 is being sought from a Santa Clara Valley Water District Grant, and $100,000 is being sought from the Open Space Authority. Remaining project funds would be provided by park impact funds and/or Measure B funds.
Estimated Project Schedule
Timeframe
Planning
Summer 2018
Project Design
Summer 2018
Right-of-Way Acquisition & Permitting
Summer 2018
Construction
Spring 2020
Project Closeout
Winter 2020
Operating Cost Impacts This facility will increase Park Maintenance operating costs in the General Fund by approximately $1,000 annually for landscape maintenance, weed control, tree trimming, utilities, occasional trail minor repair work, graffiti/vandalism, and repair/replacement of trail benches. It is expected that significant pavement repairs will be required on a 20-year cycle.
2019-2024 Six-Year Capital Improvement Program