FY 2018-19 and 2019-20 Adopted Operating and CIP Budget
CITY OF MORGAN HILL CAPITAL IMPROVEMENT PROGRAM
Expenditure Schedule & Category
Parks & Recreation: 148017
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
86200 - Professional Services
$20,000
86220 - Architecture and Design
$140,000
86360 - Construction
$1,575,493
86530 - Project Implementation
$150,000
PROJECT COST
$1,885,493
Funding Source(s)
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
f301 - Park Impact Fund
$1,885,493
FUNDING TOTALS
$1,885,493
Financial Comments Received Urban Greening Grant from the State of California in the amount of $1,761,980. Fund balances include project funding for this activity from the prior year.
Estimated Project Schedule
Timeframe
Planning
Planning for this project was completed in FY 2017/18
Project Design
Design for this project will be completed in early FY 2018/19
Construction
Construction will commence in the second quarter of FY 2018/19
Project Closeout
Closeout is anticipated in early FY 2019/20
Operating Cost Impacts This facility, when fully completed, will increase Park Maintenance operating costs by approximately $1,000 annually for litter monitoring and other maintenance. It expected that significant pavement repairs will be required on a 20-year cycle.
2019-2024 Six-Year Capital Improvement Program