Greater Gabbard Topsides Client:
Siemens Energy
Contract:
Engineering, procurement and construction (EPC)
Completion Date: 2009 Structure:
Offshore wind substation topside
Weight Topside:
2,100 tonnes Size (Length x Width x Height) Topside:
39 x 31 x 18 metres
Expertise
Management of full EPC(I) contracts, design, engineering, fabrication, transport, installation, hook-up and commissioning.
Fabrication Tonnage (Last Three Years)
14,100 tonnes
Fabrication Revenue/Turnover (Last Three Years)
Not Provided
Ability To Build Large Structures Under Cover (Yes/No)
Yes
Current Market Areas
Oil and gas and energy-related industries
Potential Market Areas
Not Provided
>