The UK Offshore Oil and Gas Fabricators Directory 2014
Projects and Markets (continued)
Buzzard Platform Client:
Nexen Petroleum UK Ltd
Contract:
Fabrication Contract (topside and bridges)
Completion Date: 2010 Structure:
Production sweetening topsides and bridge (Heerema Hartlepool)
Weight Topside:
6,000 tonnes
Bridge: 500 tonnes Size (Length x Width x Height) Topside:
60 x 36 x 42 metres
Bridge:
50 metres
Sheringham Shoal Substation Topsides Client: AREVA T&D Ltd Contract:
Engineering, procurement and construction (EPC)
Completion Date: 2010 Structure:
Two offshore wind substation topsides
Weight Topsides:
806 tonnes and 803 tonnes
Size (Length x Width x Height) Topside:
30.5 x 17.7 x 16 metres
>