PROJECTED CAPACITY INCREASES Interconnection

Capacity (GWh/d)

From Zone

To Zone

Modelled Direction Yes exit

Posušje

45.00

Ionic-Adriatic Pipeline (Croatia) Hub Bosnia & Herzegovina

DESCRIPTION OF THE PROJECT

South Interconnection of Croatia and Bosnia & Herzegovina. The pipeline will be a branch from the planned regional Ionic Adriatic Pipeline - IAP along the routing: Zagvorzd-Imotski.

EXPECTED BENEFITS

Security of Supply, Market integration, Diversification of sources, N-1 National (for BH), N-1 Regional, The aim of the project is to establish a new supply route for BH providing a diversified and reliable natural gas supply.

COMMENTS ABOUT THE PROJECT FINANCING Public financing

Private financing

Multilateral financing