Clinical Research Building/Health Village - Onix Group

ONIX GROUP Clinical Research Building (Orlando, FL) Preliminary Construction Schedule: 12/20/16

ID

Task Mode

Task Name

Duration Start

Finish

2 9 16 23 30 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 2 July August September October November December January February March April May June July

SHELL CONSTRUCTION

170 days 7/10/17 3/2/18

1 2 3 4 5 6 7 8 9

Foundations / Elevator Pits

Foundations / Elevator Pits

3 wks 3 wks 2 wks 3 wks 2 wks 3 wks 2 wks 3 wks

7/10/17 7/28/17 7/31/17 8/18/17 9/11/17 9/22/17 8/21/17 9/8/17 10/2/17 10/13/17 9/11/17 9/29/17 10/23/17 11/3/17 10/2/17 10/20/17

1st Elevated Deck - Structural Frame 1st Elevatated Deck - FRP

1st Elevated Deck ‐ Structural Frame

1st Elevatated Deck ‐ FRP

2nd Elevated Deck - Structural Frame 2nd Elevated Deck - FRP

2nd Elevated Deck ‐ Structural Frame

2nd Elevated Deck ‐ FRP

3rd Elevated Deck - Structural Frame 3rd Elevated Deck - FRP

3rd Elevated Deck ‐ Structural Frame

3rd Elevated Deck ‐ FRP

4th Elevated Deck - Structural Frame 4th Elevated Deck - FRP Roof Joists and Deck Initial Roof Membrane Level 1 - MEP Underground Rough Level 1 - Slab on Grade

4th Elevated Deck ‐ Structural Frame

4th Elevated Deck ‐ FRP Roof Joists and Deck Initial Roof Membrane

1.5 wks 11/13/17 11/22/17

10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

3 wks

10/23/17 11/10/17 11/13/17 11/17/17

1 wk

Level 1 ‐ MEP Underground Rough

10 days 10/23/17 11/3/17

Level 1 ‐ Slab on Grade Level 1 Core / Lobby

7 days

11/6/17 11/14/17

Level 1 Core / Lobby

15 wks 11/15/17 2/27/18 10 wks 11/6/17 1/12/18 10 wks 11/20/17 1/26/18 10 wks 12/4/17 2/9/18 10 wks 12/18/17 2/23/18 16 wks 11/13/17 3/2/18

Level 2 Core

Level 2 Core Level 3 Core Level 4 Core Level 5 Core

Level 3 Core

Level 4 Core

Level 5 Core

Building Envelope

Building Envelope

Elevator Installation

Elevator Installation

8 wks 6 wks

1/8/18 3/2/18 11/22/17 1/3/18

Stair Wells

Stair Wells

TENANT CONSTRUCTION

110 days 12/18/17 5/18/18 16 wks 12/27/17 4/17/18 16 wks 12/18/17 4/6/18 16 wks 1/1/18 4/20/18 16 wks 1/15/18 5/4/18 16 wks 1/29/18 5/18/18

Level 1 - Tenant Improvements

Level 1 ‐ Tenant Improvements Level 2 ‐ Tenant Improvements Level 3 ‐ Tenant Improvements Level 4 ‐ Tenant Improvements Level 5 ‐ Tenant Improvements

Level 2 - Tenant Improvements

Level 3 - Tenant Improvements

Level 4 - Tenant Improvements Level 5 - Tenant Improvem

Project: Preliminary Project Sch Date: 12/20/16

Task

Split

Milestone

Summary

Project Summary

Page 1