PU Monthly Report Volume III Issue II-August

CITY OF RALEIGH PUBLIC UTILITIES Monthly Performance Report FY 15 (July 2014-June 2015)

SEWER MAIN REPLACEMENT PROJECTS

Project Manager

Current Phase

Completion Date

Project Name

Vendor

%

Status

Reviewing 95% Plans 90% of Main Interceptor and 100% of Laterals Added Section of Sewer Replacement on Hold until July Project Information Meeting in August Working on Tunnel at Burgess

Sanitary Sewer Siphon Rehabilitation

RR

Design

Hydrostructures 95%

9/2014

Centurion Construction

Marsh Creek Sanitary Sewer Replacement

RR

Construction

95%

9/2014

Chamberlain, Clark SS Replacement

ES

Construction

Moffat Pipe

70%

3/2015

Hammond Rd SS Relocation

RR

Scoping

Dewberry

-

TBD

Gorman St. Sewer Rehab./Replacement

AB

Construction

Moffat Pipe

35%

12/2014

Desktop Review Extended Submitted to Development Review N-T-P February 2014

Aerial Crossing Replacements II

RR

PER

URS

75%

-

Aerial Crossing Replacements I

RR

Design

Dewberry

90%

-

Leafcrest Sewer Realignment

AB

Construction

Moffat Pipe

0%

12/2014

City Coordination Meeting in August

Lake Wheeler Rd Stream Relocation

RR

Design

Kimley-Horn 60%

1/2015

Flow Monitors Removed, Report Underway

Beaman Lake Creek Interceptor Evaluation

JG

Study

Hydrostructures 50%

-

Upper Pigeon House Sewer Interceptor Replacement

Advertisement in August

EN

Design

GHD

100%

2/2016

Ashe Av/Park Av/Cox Av Water and Sewer Replacement

JF Wilkerson Contracting

DL

Construction

0%

4/2015

N-T-P July 2014

Negotiations and Settlement

Eton Rd Sewer and Aerial Replacement

DL

Design

Aecom

100%

4/2014

Edens Land Corp.

Seaboard Station Sanitary Sewer Evaluation

AB

Planning

0%

12/2014

Scoping

Lower Marsh Creek Interceptor Evaluation

RR

PER

Hydrostructures 100%

6/2014

Complete

North Hills Dr, East St, E. Lenoir, Corporation Pkwy CCTV Investigation

DL

Design

Hydrostructures 50%

11/2014

Design in Process