ENTSOG GRIP CEE 2014-2023 / Annex B : Infrastructure Projects
HUNGARY
TRA-N-123
Városföld CS
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter Operator TEN-E Project ?
FGSZ Ltd FGSZ Ltd.
Not part of TEN-E Yes
Interested by PCI ? IGAs
None
Web Link
www.fgsz.hu
Private Financing (100,00%)
FGSZ (100%)
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Applied for Exemption ? Exemption granted ? Considered TPA Regime Considered Tariff Regime
End of permitting phase
# of Pipelines, nodes, CS Total Pipeline Length (km)
Regulated Regulated
2015 Q3
1
FID Construction Commissioning Last completed Phase :
2014 Q3
Total CS Power (MW) Expected Load Factor
No
2016 Q1 2017/3
+5,70
No
% Exemption in entry direction % Exemption in exit direction
0%
Planned
0%
| 110
GRIP Central Eastern Europe 2014–2023 Annex B