ENTSOG GRIP CEE 2014-2023 / Annex B : Infrastructure Projects
ENTSOG Central Eastern Europe (CEE) Gas Regional Investment Plan (GRIP) 2014-2023 / Annex B : Infrastructure Projects
GAS REGIONAL INVESTMENT PLAN 2014–2023
GRIP Central Eastern Europe
ANNEX B: INFRASTRUCTURE PROJECTS
1 Austria
Gas Connect Austria Gmbh
| 2
GRIP Central Eastern Europe 2014–2023 Annex B
AUSTRIA
TRA-N-021
Bidirectional Austrian-Czech Interconnector (BACI, formerly LBL project)
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter Operator TEN-E Project ?
Project of Common Interest Yes Gas Connect Austria GmbH Gas Connect Austria GmbH
Interested by PCI ? IGAs
None
Pipeline on Austrian territory, GAS CONNECT AUSTRIA GmbH (100%)
Pipeline on Czech territory, NET4GAS, s.r.o (100%)
Web Link
TEN-E Requests
Date of Request
Year Funding Granted
27.02.2012
2013
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Applied for Exemption ? Exemption granted ? Considered TPA Regime Considered Tariff Regime
End of permitting phase
# of Pipelines, nodes, CS Total Pipeline Length (km)
Regulated Regulated
2 +58,00
FID Construction Commissioning Last completed Phase :
Total CS Power (MW) Expected Load Factor
No
+24,00
Not relevant
2019
% Exemption in entry direction % Exemption in exit direction
0%
Planned
0%
| 3
GRIP Central Eastern Europe 2014–2023 Annex B
AUSTRIA
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone
To Zone
Modelled Direction Yes exit Yes entry
Reinthal - Bidirectional Austrian-Czech Interconnector
255,13 255,13
Hub Austria Hub Czech Republic
Hub Austria Hub Czech Republic
DESCRIPTION OF THE PROJECT
The Bidirectional-Austrian-Czech-Interconnector (BACI) will be the first bidirectional connection between the Austrian and the Czech Market.
EXPECTED BENEFITS
Security of Supply, Market Integration, Diversification of Sources, Diversification of Routes
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
| 4
GRIP Central Eastern Europe 2014–2023 Annex B
1 Austria
Tauerngasleitung GmbH
| 5
GRIP Central Eastern Europe 2014–2023 Annex B
AUSTRIA
*
TRA-N-035
Tauerngasleitung Gas Pipeline Project
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
TIGAS-Erdgas Tirol GmbH (3%)
Salzburg AG für Energie, Verkehr und Telekommunikation (18%)
Rohöl-Aufsuchungs Aktiengesellschaft (10%)
Promoter Operator TEN-E Project ?
Project of common interest Yes Tauerngasleitung GmbH Tauerngasleitung GmbH
Multilateral Financing (30,00%)
Interested by PCI ? IGAs
Energie AG Oberösterreich (18%)
None
Web Link
www.tauerngasleitung.at
Private Financing (70,00%)
KELAG-Kärntner Elektrizitäts- Aktiengesellschaft (4%)
TEN-E Requests
Date of Request
Year Funding Granted
28.04.2010 26.04.2006
2011 2007
E.ON Ruhrgas AG (47%)
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Applied for Exemption ? Exemption granted ? Considered TPA Regime Considered Tariff Regime
End of permitting phase
# of Pipelines, nodes, CS Total Pipeline Length (km)
Regulated Regulated
2014 Q4
1
FID Construction Commissioning Last completed Phase :
2014 Q2
+290,00
Total CS Power (MW) Expected Load Factor
Not yet
2015 Q1 2018/4
+66,00
No
% Exemption in entry direction % Exemption in exit direction
0%
Planned
0%
* In 2013, the sponsor’s shareholders announced that they intended to amend the sponsor’s ownership structure through a tendering process. dŚĞ d'> 'ŵď, ŚĂƐ ďĞĞŶ ĮŶĂůůLJ ůŝƋƵŝĚĂƚĞĚ ŽŶ ϭϭ͘ϰ͘ϮϬϭϰ͘
| 6
GRIP Central Eastern Europe 2014–2023 Annex B
AUSTRIA
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone
To Zone
Modelled Direction Yes exit Yes entry Yes exit Yes entry Yes exit Yes entry Yes exit Yes entry
Tauerngas Leitung (Austria) Hub Italia Tauerngas Leitung (Austria)
136,65 180,74 30,14 148,61 143,82 314,96 65,40 33,82
Tauerngas Leitung (Austria) Hub Germany (NCG) Storage Austria Hub Italia
Tarvisio - IT / Arnoldstein (Transit) - TGL
Haiming (bayernets) - DE / Burghausen-Auerbach (Austrian Storage) - TGL Haiming (bayernets) - DE / Burghausen (Transit) - TGL Haiming-Oberkappel (OGE) - DE / Burghausen (Transit) - TGL Haiming (OGE) - DE / Burghausen-Auerbach (Austrian Storage) - TGL
Hub Germany (NCG) Hub Germany (NCG) Storage Austria
Hub Germany (NCG)
Tauerngas Leitung (Austria)
Hub Germany (NCG) Hub Austria
Tauerngas Leitung (Austria)
Haiming (bayernets) - DE / Burghausen (Austrian Hub) - TGL
Hub Germany (NCG)
DESCRIPTION OF THE PROJECT
Pipeline (incl. compressor stations) in North-South direction. TGL allows feed significant volumes from different sources from South-East regions towards Central Europe.
EXPECTED BENEFITS
Security of Supply, Market integration, Reverse Flows, Diversification of sources, Diversification of routes, N-1 National, N-1 Regional, Back-up for renewables, Power-to-gas, Biogas, SoS: Investments will be necessary, especially in cross- border gas transmission capacity, with a view to diversifying sources of supply, and gas transmission systems in general, especially where capacities may be needed in an emergency to supply areas with capacity shortfalls. The TGL is in line with these objectives, which focus mainly on security of supplies. Market Integration: By linking the Central European (Southern Germany) with the South-East European (mainly Italy) natural gas market, the TGL increases interoperability between gas markets in Europe which are still separate, develop new natural gas sources for these markets and therefore significantly improve competition within a European single market for natural gas. Diversification of European natural gas supplies: By creating the infrastructure required for a functioning North-South/South-North system to develop the North African and Arab supply region, including liquefied natural gas (LNG) for the Mediterranean region, the TGL will reduce dependence on individual suppliers in the North and East.,
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
Own financing 30%. Loans 70% of which 70-80% fromcommercial banks and the rest from multilateral financing
20-30% of 70% of the overall external financing needs
| 7
GRIP Central Eastern Europe 2014–2023 Annex B
2 Bulgaria
Bulgartransgaz EAD
| 8
GRIP Central Eastern Europe 2014–2023 Annex B
BULGARIA
8*6 1
&RQVWUXFWLRQ RI QHZ JDV VWRUDJH IDFLOLW\ RQ WKH WHUULWRU\ RI %XOJDULD
1RQ ),'
Storage Facility
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter Operator TEN-E Project ?
Bulgartransgaz EAD Bulgartransgaz EAD
Project of Common Interest Yes
Interested by PCI ? IGAs
None
Web Link
http://www.bulgartransgaz.bg/en/index.php
Bulgartransgaz EAD (100%)
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Applied for Exemption ? Exemption granted ? Considered TPA Regime Considered Tariff Regime
End of permitting phase
Storage facility Working volume (mcm) Total CS Power (MW) Deliverability (mcm/d)
Regulated Regulated
Not defined yet
FID Construction Commissioning Last completed Phase :
Not relevant
Not relevant
2020
% Exemption in entry direction % Exemption in exit direction
0%
Planned
0%
| 9
GRIP Central Eastern Europe 2014–2023 Annex B
BULGARIA
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone
To Zone
Modelled Direction
DESCRIPTION OF THE PROJECT
Provision is made for the construction of new gas storage facility on the territory of Bulgaria with a view to ensuring security of supply and a stimulus to gas market liberalisation. Different opportunities for the construction of a new gas storage in suitable geological structures are considered - in salt caverns, depleted gas field (inland or offshore) or aquifer.
EXPECTED BENEFITS
Security of Supply, Market integration, N-1 National, N-1 Regional (Central Eastern Europe, South Eastern Europe, Balkan Region), ʿ̨̡̬̖̯̻̯ ̖ ̙̖̦̏̌ ̨̯ ̣̖̦̐̔̌ ̸̨̡̯̌ ̦̌ ̸̨̡̛̦̯̖̌̏̌ ̨̛̛̪̻̣̦̯̖̣̦̔ ̨̛̖̥̍ ̛̣̯̖̬̦̯̖̦̌̌̏ ̨̛̪̬̬̖̦̔ ̐̌̚ ̨̯ ʶ̡̛̛̭̪̜̭̌́ ̨̛̬̖̦̐ ̛ ̨̯ >E' ̛̛̯̖̬̥̦̣̯̖̌ ̏ ̨̛̬̖̦̐̌ ̛ ̺̖ ̨̭̣̱̙̍̏̌ ̦̖ ̨̭̥̌ ̶̨̛̛̦̦̣̦͕̌̌́ ̨̦ ̛ ̨̛̛̬̖̦̣̦̐̌́ ̨̐̌̏̚ ̪̬̌̌̚ ̭̣̖̔ ̨̨̛̪̣̦̬̦̯̌̌ ̛̬̙̦̖̐̌̔̌̚ ̦̌ ̨̛̦̯̖̏ ̛̛̥̖̙̱̭̭̯̖̥̦̔ ̡̛̬̻̏̚ ̭̻̭ ̛̭̻̭̖̦̯̖̔ ̛̭̯̬̦̌͘
,
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
| 10
GRIP Central Eastern Europe 2014–2023 Annex B
BULGARIA
TRA-N-140
Interconnection Turkey-Bulgaria
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter Operator TEN-E Project ?
Bulgartransgaz EAD Bulgartransgaz EAD
Project of Common Interest Yes
Interested by PCI ? IGAs
2
Web Link
http://www.bulgartransgaz.bg/en/index.php
Bulgartransgaz EAD for the gas pipeline section on the territory of Bulgaria (100%)
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Applied for Exemption ? Exemption granted ? Considered TPA Regime Considered Tariff Regime
End of permitting phase
# of Pipelines, nodes, CS Total Pipeline Length (km)
Not applicable Not applicable
2 +205,00
FID Construction Commissioning Last completed Phase :
Total CS Power (MW) Expected Load Factor
Not relevant
Not relevant
2016
% Exemption in entry direction % Exemption in exit direction
0%
Planned
0%
| 11
GRIP Central Eastern Europe 2014–2023 Annex B
BULGARIA
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone
To Zone
Modelled Direction Yes entry
Hub Turkey (Imports)
Interconnector ITB (Turkey - Bulgaria)
92,00
Hub Greece
DESCRIPTION OF THE PROJECT
The interconnection is foreseen to be built as a development to the existing connection of Bulgartransgaz EAD and Botas ^͘ʤ͘ – Turkey systems by creating the technical opportunity for enabling bi-directional physical flow of natural gas between both systems. Thus a significantly greater security of gas supply to our country can be achieved, meeting the N-1 security standard and diversification of natural gas supply sources. Preliminary plans are for a staged project development, with the commissioning in 2014 or 2015 of the first stage depending on the development of the Turkish gas transmission system.
EXPECTED BENEFITS
Security of Supply, Market integration, Reverse Flows, Diversification of sources, Diversification of routes, N-1 National, N-1 Regional (Central and Eastern Europe, South Eastern Europe, Balkan Region), The interconnection Turkey- Bulgaria is a key project whose realization shall lead to the increase of the security of supply and the opportunity for diversification of gas supply not only to Bulgaria, but to the Central and South-Eastern Europe region as well. The project contributes directly to the diversification of gas sources: alternative gas producers - countries from the Caspian region, Turkish LNG terminals and Middle East.,
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
| 12
GRIP Central Eastern Europe 2014–2023 Annex B
BULGARIA
TRA-N-298
Rehabilitation, Modernization and Expansion of the National Transmission System
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter Operator TEN-E Project ?
Bulgartransgaz EAD Bulgartransgaz EAD
Project of Common Interest Yes
Interested by PCI ? IGAs
None
Web Link
http://www.bulgartransgaz.bg/en/index.php
Bulgartransgaz EAD (100%)
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Applied for Exemption ? Exemption granted ? Considered TPA Regime Considered Tariff Regime
End of permitting phase
# of Pipelines, nodes, CS Total Pipeline Length (km)
Not applicable Not applicable
FID Construction Commissioning Last completed Phase :
2015
Total CS Power (MW) Expected Load Factor
Not relevant
Not relevant
2017
% Exemption in entry direction % Exemption in exit direction
0%
0%
| 13
GRIP Central Eastern Europe 2014–2023 Annex B
BULGARIA
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone
To Zone
Modelled Direction
DESCRIPTION OF THE PROJECT
A set of activities involving rehabilitation, modernisation and expansion of the existing national gas transmission infrastructure with a view to guaranteeing the possibility of the national gas transmission system to ensure the transport of sufficient natural gas volumes through the territory of the country using the planned new interconnections to other countries from the region of South Eastern, Central and Eastern Europe and in the context of the large cross-border gas projects in the region. The project mostly include compressor stations modernisation (CS Valchi Dol and CS Polski Senovets) as well as in-line inspections, complete overhauls and replacement of gas pipeline sections of the main gas pipelines that are part of the annularly built gas transmission system and construction regulating lines at the exits of gas pipeline branches off the main and transit gas pipeline to enhance its reliability, security and capacity.
EXPECTED BENEFITS
Security of Supply, Market integration, Reverse Flows, Diversification of sources, Diversification of routes, N-1 National, N-1 Regional (Central and Eastern Europe, South Eastern Europe, Balkan Region), The modernisation, rehabilitation and expansion of the existing gas transmission network are directly linked to the planned new interconnections with Greece (IGB), Romania (IBR), Turkey (ITB) and Serbia (IBS), the integration of the national and the transit gas transmission system on the territory of Bulgaria and the development of the large cross-border gas projects in the region. The efficient use of the new entry and exit points from/to Bulgartransgaz gas transmission networks is directly linked to the technical possibilities of the existing gas transmission infrastructure on the territory of Bulgaria to ensure sufficient capacity and suitable technical conditions to accommodate the transport of the planned new natural gas quantities and to the available storage capacity and and the expansion of the gas storage facility in Chiren unique on the territory of the country accordingly. ,
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
| 14
GRIP Central Eastern Europe 2014–2023 Annex B
BULGARIA
8*6 1
8*6 &KLUHQ ([SDQVLRQ
1RQ ),'
Storage Facility
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter Operator TEN-E Project ?
Bulgartransgaz EAD Bulgartransgaz EAD
Project of Common Interest Yes
Interested by PCI ? IGAs
None
Web Link
http://www.bulgartransgaz.bg/en/index.php
Bulgartransgaz EAD (100%)
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Applied for Exemption ? Exemption granted ? Considered TPA Regime Considered Tariff Regime
End of permitting phase
Storage facility Working volume (mcm) Total CS Power (MW) Deliverability (mcm/d)
Regulated Regulated
UGS Chiren +450,00
FID Construction Commissioning Last completed Phase :
2014
Not relevant
+5,80 +5,80
Not relevant
2017
% Exemption in entry direction % Exemption in exit direction
0%
0%
| 15
GRIP Central Eastern Europe 2014–2023 Annex B
BULGARIA
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone
To Zone
Modelled Direction Yes exit Yes entry Yes exit Yes entry
Storage Bulgaria (NGTS) Hub Bulgaria (NGTS) Storage Bulgaria (NGTS) Hub Bulgaria (NGTS)
UGS - BG - Chiren - Bulgartransgaz
65,00 65,00 65,00 65,00
Hub Bulgaria (NGTS) Storage Bulgaria (NGTS) Hub Bulgaria (NGTS) Storage Bulgaria (NGTS)
DESCRIPTION OF THE PROJECT
The project for expansion of the existing gas storage facility Chiren consists of staged capacity increse of the gas storage facility ʹ higher stored gas volumes, higher pressures in the gas reservoir and reaching higher average daily withdrawal and injection flow rates. Two options of reaching maximum capacities are mainly under consideration:
ʹ ƵƉ ƚŽ ϭϯϬ ďĂƌ ĨŽŵĂƚŝŽŶ ƉƌĞƐƐƵƌĞ͕ ĂĐƚŝǀĞ ŐĂƐ ϳϮϬ ŵĐŵ ĂŶĚ ĚĂŝůLJ ƉƌŽĚƵĐƚŝŽŶ ĂŶĚ ǁŝƚŚĚƌĂǁĂů ĨůŽǁ ϭϬ ŵĐŵ͘ ʹ ƵƉ ƚŽ ϭϱϬ ďĂƌ ĨŽƌŵĂƚŝŽŶ ƉƌĞƐƐƵƌĞ͕ ĂĐƚŝǀĞ ŐĂƐ ϭϬϬϬ ŵĐŵ ĂŶĚ ĚĂŝůLJ ƉƌŽĚƵĐƚŝŽŶ ĂŶĚ ǁŝƚŚĚƌĂǁĂů ĨůŽǁ ϭϬ ŵĐŵ͘
EXPECTED BENEFITS
Security of Supply, Market integration, N-1 National, N-1 Regional (Central Eastern Europe, South Eastern Europe, Balkan Region), In this moment UGS Chiren covers mainly seasonal fluctuations in domestic consumption and ensures the security of supply. Additional stored volumes and higher withdrawal and injection rates will serve Bulgarian and regional gas markets (Greek, Romanian, Macedonian and Serbian) via the existing and the new interconnections - IBR, IGB, / ^ ĂŶĚ /d ͘ dŚĞ ĞdžƉĂŶƐŝŽŶ ŽĨ ƚŚĞ h'^ ƚŽŐĞƚŚĞƌ ǁŝƚŚ ƚŚĞ ƉůĂŶŶĞĚ ŐĂƐ ƉŝƉĞůŝŶĞ ƉƌŽũĞĐƚƐ ŝƐ ŽĨ ŚŝŐŚ ŝŵƉŽƌƚĂŶĐĞ ĨŽƌ ƚŚĞ ŝŵƉůĞŵĞŶƚĂƚŝŽŶ ŽĨ ƚŚĞ /ŶĨƌĂƐƚƌƵĐƚƵƌĞ ^ƚĂŶĚĂƌĚ EͲϭ ;ZĞŐƵůĂƚŝŽŶ lzh EŽ ϵϵϰͬϮϬϭϬ Ϳ͘
,
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
| 16
GRIP Central Eastern Europe 2014–2023 Annex B
2 Bulgaria ICGB EAD
| 17
GRIP Central Eastern Europe 2014–2023 Annex B
BULGARIA
TRA-N-149
Interconnector Greece Bulgaria - IGB
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter Operator TEN-E Project ?
DEPA S.A. ICGB a.d.
Not part of TEN-E Yes
Interested by PCI ? IGAs
None
IGI Poseidon S.A. (50%)
Bulgarian Energy Holding EAD (50%)
Web Link
www.icgb.eu
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Applied for Exemption ? Exemption granted ? Considered TPA Regime Considered Tariff Regime
End of permitting phase
# of Pipelines, nodes, CS Total Pipeline Length (km)
Negotiated (e.g. Exemption) Negotiated (e.g. Exemption)
2014 Q1
2
FID Construction Commissioning Last completed Phase :
2014 Q2
+182,00
Total CS Power (MW) Expected Load Factor
Yes
2014 Q3 2016/1
+10,00
Not yet
% Exemption in entry direction % Exemption in exit direction
0%
Permitting
0%
| 18
GRIP Central Eastern Europe 2014–2023 Annex B
BULGARIA
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone
To Zone
Modelled Direction Yes entry Yes exit Yes entry Yes exit
Komotini - TAP / IGB
82,00 82,00 82,00 82,00
Interconnector Greece-Bulgaria Trans-Adriatic Pipeline (Greece) Interconnector Greece-Bulgaria Hub Bulgaria (NGTS)
Trans-Adriatic Pipeline (Greece) Interconnector Greece-Bulgaria (Bulgaria) Hub Bulgaria (NGTS) Interconnector Greece-Bulgaria (Bulgaria)
Stara Zagora - IGB / BG
DESCRIPTION OF THE PROJECT
An onshore natural gas pipeline that will connect Komotini in Greece to Stara Zagora in Bulgaria. The IGB pipeline is being developed by ICGB AD, with shareholders IGI-Poseidon S.A. and Bulgarian Energy Holding EAD
EXPECTED BENEFITS
Security of Supply, Market integration (Greece, Bulgaria, Romania, Hungary, FYROM, Serbia), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (Greece, Bulgaria), N-1 Regional (NSI East Gas), Back-up for renewables, Power-to-gas, The project will contribute significantly in the itegration of the market area, specifically the South Eastern Europe, and will allow to alleviate to a great extend the dependency of countries in the area to a single source/counterpart.Taking into account that the objective of the project is to bring additional import quantities of natural gas in Bulgaria and South Eastern Europe it significantly improves the resilience of the system in both short (the additional quantities will be able to cover daily peak demands) and long term. Specifically for the long term, the diversification in route, supply source as well as counterparts will have a great positive impact on the resilience of the system and will be able to cater to any forecasted increase in demand over the coming years. The impact of the project in the systems flexibility under disruption (n-1 rule) will be significant taking into account that it will create a new interconnections carrying gas from a new source allowing new counterparts to enter the market. A possible disruption in any of the other import sources (including the regional disruption of Russian gas) will NOT AFFECT this one having a great positive impact on the remaining flexibility of the system.,
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
| 19
GRIP Central Eastern Europe 2014–2023 Annex B
2 Bulgaria
Ministry of Economy and Energy of Republic of Bulgaria
| 20
GRIP Central Eastern Europe 2014–2023 Annex B
BULGARIA
TRA-N-137
Interconnection Bulgaria - Serbia
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter Operator TEN-E Project ?
Bulgarian Ministry of Economy and energy (MEE) Bulgartransgaz EAD
Not part of TEN-E Yes
Interested by PCI ? IGAs
3
ƵůŐĂƌŝĂŶ ƐĞĐƚŝŽŶ͕ DŝŶŝƐƚƌLJ ŽĨ ĐŽŶŽŵLJ
^ĞƌďŝĂŶ ƐĞĐƚŝŽŶ͕ ^ĞƌďŝũĂŐĂƐ ;ϭϬϬйͿ
ĂŶĚ ŶĞƌŐLJ ŽĨ ƵůŐĂƌŝĂ ;ϭϬϬйͿ
Web Link
ǁǁǁ͘ďƵůŐĂƌƚƌĂŶƐŐĂnj͘ďŐ
WƵďůŝĐ &ŝŶĂŶĐŝŶŐ ;ϵϵ͕ϬϬйͿ
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Applied for Exemption ? Exemption granted ? Considered TPA Regime Considered Tariff Regime
End of permitting phase
# of Pipelines, nodes, CS Total Pipeline Length (km)
Regulated Regulated
2014
2
FID Construction Commissioning Last completed Phase :
2014
+155,00
Total CS Power (MW) Expected Load Factor
No
2015 2015
No
% Exemption in entry direction % Exemption in exit direction
0%
Planned
0%
| 21
GRIP Central Eastern Europe 2014–2023 Annex B
BULGARIA
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone
To Zone
Modelled Direction Yes exit Yes entry
Hub Bulgaria (NGTS) Hub Serbia
Interconnector BG RS
51,00 51,00
Hub Bulgaria (NGTS) Hub Serbia
DESCRIPTION OF THE PROJECT
dŚŝƐ ŝƐ ƚŚĞ ĨŝƌƐƚ ŝŶƚĞƌĐŽŶŶĞĐƚŝŽŶ ďĞƚǁĞĞŶ ƚŚĞ ŐĂƐ ƚƌĂŶƐŵŝƐƐŝŽŶ ƐLJƐƚĞŵƐ ŽĨ ^ĞƌďŝĂ ĂŶĚ ƵůŐĂƌŝĂ͘ dŚĞ ƉƌŽũĞĐƚ ĞƐƚĂďůŝƐŚĞƐ Ă ĐŽŶŶĞĐƚŝŽŶ ďĞƚǁĞĞŶ ƚŚĞ ƵůŐĂƌŝĂŶ ĂŶĚ ^ĞƌďŝĂŶ ŐĂƐ ŵĂƌŬĞƚƐ ƚŚĂƚ ĐƵƌƌĞŶƚůLJ ĂƌĞ ŶŽƚ ĐŽŶŶĞĐƚĞĚ͘
EXPECTED BENEFITS
^ĞĐƵƌŝƚLJ ŽĨ ^ƵƉƉůLJ͕ DĂƌŬĞƚ ŝŶƚĞŐƌĂƚŝŽŶ͕ ZĞǀĞƌƐĞ &ůŽǁƐ͕ ŝǀĞƌƐŝĨŝĐĂƚŝŽŶ ŽĨ ƐŽƵƌĐĞƐ͕ ŝǀĞƌƐŝĨŝĐĂƚŝŽŶ ŽĨ ƌŽƵƚĞƐ͕ EͲϭ EĂƚŝŽŶĂů͕ EͲϭ ZĞŐŝŽŶĂů͕ dŚĞ ƉƌŽũĞĐƚƐ ůŝƐƚĞĚ ĂďŽǀĞ ƐŚŽƵůĚ ĞŶŚĂŶĐĞ ƚŚĞ ƐLJƐƚĞŵ ĨůĞdžŝďŝůŝƚLJ ĂŶĚ ĐŽŶƚƌŝďƵƚĞ ƚŽ ƚŚĞ ƐĞĐƵƌŝƚLJ ŽĨ ƐƵƉƉůLJ ǁŝƚŚŝŶ ƚŚĞ ƌĞŐŝŽŶ ;ŝŶĐƌĞĂƐĞĚ ŝŶƚĞƌĐŽŶŶĞĐƚŝŽŶ ďĞƚǁĞĞŶ ƵůŐĂƌŝĂ ĂŶĚ ^ĞƌďŝĂͿ͕
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
ŽŵƉĞƚŝƚŝǀĞŶĞƐƐ ŽĨ ƚŚĞ ƵůŐĂƌŝĂŶ ĐŽŶŽŵLJ KƉĞƌĂƚŝŽŶĂů WƌŽŐƌĂŵŵĞ
| 22
GRIP Central Eastern Europe 2014–2023 Annex B
2 Bulgaria
South Stream Bulgaria AD (Bulgarian Shareholder Bulgarian Energy Holding EAD)
| 23
GRIP Central Eastern Europe 2014–2023 Annex B
BULGARIA
TRA-N-308
South Stream Bulgaria - Stage I
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
South Stream Bulgaria AD (Bulgarian Bulgartransgaz EAD
Promoter Operator TEN-E Project ?
Not part of TEN-E Not defined yet
Interested by PCI ? IGAs
None
Web Link
Bulgartransgaz EAD (100%)
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Applied for Exemption ? Exemption granted ? Considered TPA Regime Considered Tariff Regime
End of permitting phase
# of Pipelines, nodes, CS Total Pipeline Length (km)
Not applicable Not applicable
FID Construction Commissioning Last completed Phase :
Total CS Power (MW) Expected Load Factor
Not relevant
Not relevant
2015
% Exemption in entry direction % Exemption in exit direction
0%
0%
| 24
GRIP Central Eastern Europe 2014–2023 Annex B
BULGARIA
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone
To Zone
Modelled Direction Yes entry
South Stream into Bulgaria (BG)
162,50
South Stream (Russia)
Hub Bulgaria (NGTS)
DESCRIPTION OF THE PROJECT
First stage of the South Stream interconnection to the Bulgarian network, as understood by ENTSOG based on e-mail exchange.
EXPECTED BENEFITS
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
| 25
GRIP Central Eastern Europe 2014–2023 Annex B
BULGARIA
TRA-N-309
South Stream Bulgaria - Stage II
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
South Stream Bulgaria AD (Bulgarian Bulgartransgaz EAD
Promoter Operator TEN-E Project ?
Not part of TEN-E Not defined yet
Interested by PCI ? IGAs
None
Web Link
Bulgartransgaz EAD (100%)
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Applied for Exemption ? Exemption granted ? Considered TPA Regime Considered Tariff Regime
End of permitting phase
# of Pipelines, nodes, CS Total Pipeline Length (km)
Not applicable Not applicable
FID Construction Commissioning Last completed Phase :
Total CS Power (MW) Expected Load Factor
Not relevant
Not relevant
2016
% Exemption in entry direction % Exemption in exit direction
0%
0%
| 26
GRIP Central Eastern Europe 2014–2023 Annex B
BULGARIA
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone
To Zone
Modelled Direction Yes entry
South Stream into Bulgaria (BG)
62,10
South Stream (Russia)
Hub Bulgaria (NGTS)
DESCRIPTION OF THE PROJECT
Second stage of the South Stream interconnection to the Bulgarian network, as understood by ENTSOG based on e-mail exchange.
EXPECTED BENEFITS
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
| 27
GRIP Central Eastern Europe 2014–2023 Annex B
BULGARIA
TRA-N-310
South Stream Bulgaria - Stage III
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
South Stream Bulgaria AD (Bulgarian Bulgartransgaz EAD
Promoter Operator TEN-E Project ?
Not part of TEN-E Not defined yet
Interested by PCI ? IGAs
None
Web Link
Bulgartransgaz EAD (100%)
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Applied for Exemption ? Exemption granted ? Considered TPA Regime Considered Tariff Regime
End of permitting phase
# of Pipelines, nodes, CS Total Pipeline Length (km)
Not applicable Not applicable
FID Construction Commissioning Last completed Phase :
Total CS Power (MW) Expected Load Factor
Not relevant
Not relevant
2017
% Exemption in entry direction % Exemption in exit direction
0%
0%
| 28
GRIP Central Eastern Europe 2014–2023 Annex B
BULGARIA
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone
To Zone
Modelled Direction Yes entry
South Stream into Bulgaria (BG)
15,50
South Stream (Russia)
Hub Bulgaria (NGTS)
DESCRIPTION OF THE PROJECT
Third and final stage of the South Stream interconnection to the Bulgarian network, as understood by ENTSOG based on e-mail exchange.
EXPECTED BENEFITS
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
| 29
GRIP Central Eastern Europe 2014–2023 Annex B
3 Croatia
Plinacro d.o.o.
| 30
GRIP Central Eastern Europe 2014–2023 Annex B
CROATIA
TRA-N-068
Ionian Adriatic Pipeline
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
Croatia (From Split to Montenegro border), Plinacro Ltd; Ministry of Economy (Croatia) (100%)
Fieri to Montenegro border, Ministry of Economy , Trade and Energy (Albania) (100%)
Promoter Operator TEN-E Project ?
Plinacro Ltd Plinacro Ltd
Not part of TEN-E Yes
Interested by PCI ? IGAs
2
Web Link
www.plinacro.hr
Bosnia and Herzegovina, BH Gas (Bosnia and Herzegovina); Ministry of Foreign Trade and Economic Relations (BiH) (100%)
Montenegro, Ministry of Economy (Montenegro) (100%)
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Applied for Exemption ? Exemption granted ? Considered TPA Regime Considered Tariff Regime
End of permitting phase
# of Pipelines, nodes, CS Total Pipeline Length (km)
Regulated Regulated
3 +540,00
FID Construction Commissioning Last completed Phase :
Total CS Power (MW) Expected Load Factor
No
2015 2020
No
% Exemption in entry direction % Exemption in exit direction
0%
Planned
0%
| 31
GRIP Central Eastern Europe 2014–2023 Annex B
CROATIA
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone
To Zone
Modelled Direction Yes exit Yes entry Yes entry Yes exit Yes exit
30,00 150,00 75,00
Ionic-Adriatic Pipeline (Croatia) Ionic-Adriatic Pipeline (Croatia) Ionic-Adriatic Pipeline (Croatia) Trans-Adriatic Pipeline (Greece) Ionic-Adriatic Pipeline (Croatia)
Ionic-Adriatic Pipeline (Croatia) Hub Croatia Hub Bosnia Herzegovina Hub Albania
Ionic-Adriatic Pipeline - IAP / AB Trans-Adriatic Pipeline - TAP / Ionic-Adriatic Pipeline - IAP Ionic-Adriatic Pipeline - IAP / Split - HR Ionic-Adriatic Pipeline - IAP / BH
15,00 30,00
Ionic-Adriatic Pipeline - IAP / ME
Hub Montenegro
DESCRIPTION OF THE PROJECT
The pipeline will cross the territory along the Adriatic coast from Fieri in Albania via Montenegro to Split in Croatia and will be linked to the existing Croatian gas transmission system (main direction Bosiljevo ʹ Split). The Ionian-Adriatic Pipeline is considered a part of the Energy Community Gas Ring, which is the concept of gasification for the entire region, proposed by the WB Study and accepted by the Gas Fora of the Energy Community.
EXPECTED BENEFITS
Security of Supply, Market integration (Market Integration benefits for Croatia and the region (Albania, Montenegro, Bosnia and Herzegovina and neighbouring countries), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National, N-1 Regional (Balkan region ), Back-up for renewables,
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
| 32
GRIP Central Eastern Europe 2014–2023 Annex B
CROATIA
Interconnection Croatia-Bosnia and Herzegovina (Licka Jesenica-Rakovica-Trzac-Bosanska .UXSD ZLWK EUDQFKHV WR %LKDü DQG 9HOLND .ODGXVD
TRA-N-303
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter Operator TEN-E Project ?
Plinacro Ltd
Not part of TEN-E No Plinacro Ltd, BH Gas
Interested by PCI ? IGAs
None
ƉĂƌƚŝŶ Θ,͕ , 'ĂƐ ;ϭϬϬйͿ
ƌŽĂƚŝĂŶ ƉĂƌƚ ͕ WůŝŶĂĐƌŽ Ě͘Ž͘Ž͘ ;ϭϬϬйͿ
Web Link
ǁǁǁ͘ƉůŝŶĂĐƌŽ͘Śƌ
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Considered TPA Regime Considered Tariff Regime Applied for Exemption ? Exemption granted ?
End of permitting phase
# of Pipelines, nodes, CS Total Pipeline Length (km)
2 +30.00
Regulated Regulated
FID Construction Commissioning Last completed Phase :
Total CS Power (MW) Expected Load Factor
No
No
2023
% Exemption in entry direction % Exemption in exit direction
0%
Planned
0%
| 33
GRIP Central Eastern Europe 2014–2023 Annex B
CROATIA
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone Hub Croatia
To Zone
Modelled Direction Yes exit
Rakovica (HR) / Trzac (BA)
45.00
Hub Bosnia and Herzegovina
DESCRIPTION OF THE PROJECT
/ŶƚĞƌĐŽŶŶĞĐƚŝŽŶ ƌŽĂƚŝĂͲ ŽƐŶŝĂ ĂŶĚ ,ĞƌnjĞŐŽǀŝŶĂ ŽŶ ƌŽƵƚĞ >ŝĐŬĂ :ĞƐĞŶŝĐĂͲZĂŬŽǀŝĐĂ ŝŶ ƌŽĂƚŝĂ ƚŽ ďŽƌĚĞƌ ǁŝƚŚ ŽƐŶŝĂ ĂŶĚ ,ĞƌnjĞŐŽǀŝŶĂ͘ ŽƐŶŝĂŶ ƉĂƌƚ ŝƐ ĨƌŽŵ dƌnjĂĐ ƚŽ ŽƐĂŶƐŬĂ <ƌƵƉĂ ǁŝƚŚ ďƌĂŶĐŚĞƐ ƚŽ ŝŚĂđ ĂŶĚ sĞůŝŬĂ <ůĂĚƵƐĂ͘
EXPECTED BENEFITS
^ĞĐƵƌŝƚLJ ŽĨ ^ƵƉƉůLJ͕ DĂƌŬĞƚ ŝŶƚĞŐƌĂƚŝŽŶ͕ ŝǀĞƌƐŝĨŝĐĂƚŝŽŶ ŽĨ ƐŽƵƌĐĞƐ͕ EͲϭ EĂƚŝŽŶĂů ;ĨŽƌ Θ,Ϳ͕ EͲϭ ZĞŐŝŽŶĂů͕ dŚĞ Ăŝŵ ŽĨ ƚŚĞ ƉƌŽũĞĐƚ ŝƐ ƚŽ ĂƐƐĞƐƐ ƚŚĞ ĨĞĂƐŝďŝůŝƚLJ ŽĨ ƉƌŽǀŝĚŝŶŐ ŐĂƐ ƐƵƉƉůLJ ƚŽ ƚŚĞ hŶĂͲ^ĂŶĂ ĂŶƚŽŶ ŝŶ Θ, ĨƌŽŵ ƚŚĞ ƌŽĂƚŝĂŶ ŐĂƐ ƐƵƉƉůLJ ŶĞƚǁŽƌŬ͘ dŚŝƐ ƐƵƉƉůLJ ŶĞƚǁŽƌŬ ǁŝůů ďĞ ĨƌŽŵ ƚŚĞ >ŝēŬĂ :ĞƐĞŶŝĐĂ ŐĂƐ ƚƌĂŶƐŵŝƐƐŝŽŶ ŶŽĚĞ ŝŶ ƌŽĂƚŝĂ ǀŝĂ >ŝŬĂ ƚŽ ƚŚĞ ,Zͬ Θ, ďŽƌĚĞƌ ĂŶĚ ĨƌŽŵ ƚŚĞƌĞ ƚŽ ŽƐĂŶƐŬĂ <ƌƵƉĂ ǁŝƚŚ ďƌĂŶĐĞƐ ƚŽ ŝŚĂđ ĂŶĚ ǀĞůŝŬĂ <ůĂĚƵƓĂ ŝŶ hŶĂͲ^ĂŶĂ ĂŶƚŽŶ͘ dŚĞ ĞdžƚĞŶƐŝŽŶ ŽĨ ƚŚĞ ŐĂƐ ƚƌĂŶƐŵŝƐƐŝŽŶ ŝŶ ƌŽĂƚŝĂ ƚŽ ƚŚĞ ďŽƌĚĞƌ ǁŝƚŚ Θ, ǁŝůů ĂůůŽǁ ĂĚĚŝƚŝŽŶĂů ŐĂƐŝĨŝĐĂƚŝŽŶ ŝŶ ƚŚĞ ƉĂƌƚ ŽĨ ƌŽĂƚŝĂ ĂůŽŶŐ ƚŚĞ ƉŝƉĞůŝŶĞ ƌŽƵƚĞ͕͘
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
| 34
GRIP Central Eastern Europe 2014–2023 Annex B
CROATIA
TRA-N-066
Interconnection Croatia/Bosnia and Herzegovina (Slobodnica- Bosanski Brod-Zenica)
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter Operator TEN-E Project ?
Plinacro Ltd
Not part of TEN-E NO Plinacro Ltd, BH Gas
Interested by PCI ? IGAs
2
ƌŽĂƚŝĂ͕ ^ůŽďŽĚŶŝĐĂͲ ŽƐĂŶƐŬŝ ƌŽĚ ;ďŽƌĚĞƌͿ͕ WůŝŶĂĐƌŽ ;ϭϬϬйͿ
Θ,͕ ŽƐĂŶƐŬŝ ƌŽĚ Ͳ ĞŶŝĐĂ͕ , 'ĂƐ ;ϭϬϬйͿ
Web Link
ǁǁǁ͘ƉůŝŶĂĐƌŽ͘Śƌ
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Applied for Exemption ? Exemption granted ? Considered TPA Regime Considered Tariff Regime
End of permitting phase
# of Pipelines, nodes, CS Total Pipeline Length (km)
Regulated Regulated
1 +6,00
FID Construction Commissioning Last completed Phase :
Total CS Power (MW) Expected Load Factor
No
2018 2019
No
+0,90
% Exemption in entry direction % Exemption in exit direction
0%
Planned
0%
| 35
GRIP Central Eastern Europe 2014–2023 Annex B
CROATIA
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone Hub Croatia
To Zone
Modelled Direction Yes exit
Slobodnica- Bosanski Brod-Zenica
44,00
Hub Bosnia Herzegovina
DESCRIPTION OF THE PROJECT
dŚĞ ƉŝƉĞůŝŶĞ ĐŽǀĞƌƐ ƚŚĞ ĐŽƵŶƚƌŝĞƐ ƌŽĂƚŝĂ ĂŶĚ ŽƐŶŝĂ ĂŶĚ ,ĞƌnjĞŐŽǀŝŶĂ ĂŶĚ ŝƚ ǁŝůů ďĞ ƚŚĞ ƉĂƌƚ ŽĨ ŶĞƌŐLJ ŽŵŵƵŶŝƚLJ ZŝŶŐ͘ dŚĞ ƉŝƉĞůŝŶĞ ŐŽĞƐ ĨƌŽŵ ^ůĂǀŽŶƐŬŝ ƌŽĚ ;^ůŽďŽĚŶŝĐĂͿ ŝŶ ƌŽĂƚŝĂ͕ ŝƚ ǁŝůů ĐƌŽƐƐ ƚŚĞ ^ĂǀĂ ƌŝǀĞƌ ƚŽ ŽƐĂŶƐŬŝ ƌŽĚ ŝŶ ŽƐŶŝĂ ĂŶĚ ,ĞƌnjĞŐŽǀŝŶĂ ǁŝƚŚ ĨƵƌƚĞƌ ĞdžƚĞŶƐŝŽŶ ƚŽ ĞŶŝĐĂ͘
EXPECTED BENEFITS
DĂƌŬĞƚ ŝŶƚĞŐƌĂƚŝŽŶ͕ ZĞǀĞƌƐĞ &ůŽǁƐ͕ EͲϭ ZĞŐŝŽŶĂů ;&Žƌ ŽƐŶŝĂ ĂŶĚ ,ĞƌnjĞŐŽǀŝŶĂͿ͕ ĂĐŬͲƵƉ ĨŽƌ ƌĞŶĞǁĂďůĞƐ͕ /ƚ ǁŝůů ďĞ ŶĞǁ ŝŶƚĞƌĐŽŶŶĞĐƚŝŽŶ͕ ŶĞǁ ĞŶƚƌLJ ƉŽŝŶƚ ĂŶĚ ƚƌĂŶƐŵŝƐƐŝŽŶ ƌŽƵƚĞ ĨŽƌ ƚŚĞ ŶĞĞĚƐ ŽĨ Θ,͖ ŝƚ ǁŝůů ďĞ ^Ž^ ĂŶĚ ĚŝǀĞƌƐŝĨŝĐĂƚŝŽŶ ŽĨ ƐƵƉƉůLJ ƌŽƵƚĞ ĨŽƌ ŽƐŶŝĂ ĂŶĚ ,ĞƌnjĞŐŽǀŝŶĂ͕
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
| 36
GRIP Central Eastern Europe 2014–2023 Annex B
CROATIA
TRA-N-302
Interconnection Croatia-Bosnia and Herzegovina (South)
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter Operator TEN-E Project ?
Plinacro Ltd
Not part of TEN-E No Plinacro Ltd, BH Gas
Interested by PCI ? IGAs
None
Croatian part of both options, Plinacro d.o.o. (100%)
parts in B&H, BH Gas (100%)
Web Link
www.plinacro.hr
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Considered TPA Regime Considered Tariff Regime Applied for Exemption ? Exemption granted ?
End of permitting phase
# of Pipelines, nodes, CS Total Pipeline Length (km)
3 +29.00
Regulated Regulated
FID Construction Commissioning Last completed Phase :
Total CS Power (MW) Expected Load Factor
No
No
2018
% Exemption in entry direction % Exemption in exit direction
0%
Planned
0%
| 37
GRIP Central Eastern Europe 2014–2023 Annex B
CROATIA
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone
To Zone
Modelled Direction Yes exit
ĂŐǀŽnjĚͲ/ŵŽƚƐŬŝͲWŽƐƵƓũĞ
45.00
Ionic-Adriatic Pipeline (Croatia)
Hub Bosnia and Herzegovina
DESCRIPTION OF THE PROJECT
South Interconnection of Croatia and B&H - the pipeline is actually branch from planned regional Ionic Adriatic Pipeline - IAP.
EXPECTED BENEFITS
Security of Supply, Market integration, Diversification of sources, N-1 National (for B&H), N-1 Regional, The aim of the project is to establish a new supply route for B&H providing a diversified and reliable natural gas supply.,
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
| 38
GRIP Central Eastern Europe 2014–2023 Annex B
CROATIA
TRA-N-070
,QWHUFRQQHFWLRQ &URDWLD 6HUELD 6OREGQLFD 6RWLQ &URDWLD %DþNR 1RYR 6HOR 6HUELD
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter Operator TEN-E Project ?
Plinacro Ltd Plinacro Ltd
Not part of TEN-E NO
Interested by PCI ? IGAs
None
ƌŽĂƚŝĂŶ ƐĞĐƚŝŽŶ͕ WůŝŶĂĐƌŽ ;ϭϬϬйͿ
^ĞƌďŝĂŶ ƐĞĐƚŝŽŶ͕ ^ƌďŝũĂŐĂƐ ;ϭϬϬйͿ
Web Link
ǁǁǁ͘ƉůŝŶĂĐƌŽ͘Śƌ
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Applied for Exemption ? Exemption granted ? Considered TPA Regime Considered Tariff Regime
End of permitting phase
# of Pipelines, nodes, CS Total Pipeline Length (km)
Regulated Regulated
2 +102,00
FID Construction Commissioning Last completed Phase :
Total CS Power (MW) Expected Load Factor
No
2018 2023
No
% Exemption in entry direction % Exemption in exit direction
0%
Planned
0%
| 39
GRIP Central Eastern Europe 2014–2023 Annex B
CROATIA
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone Hub Croatia
To Zone
Modelled Direction Yes exit
^ůŽďŽĚŶŝĐĂ Ͳ ^ŽƚŝŶ ;,ZͿ ͬ ĂēŬŽ EŽǀŽ ^ĞůŽ ;Z^Ϳ
176,00
Hub Serbia
DESCRIPTION OF THE PROJECT
ŽǀĞƌŝŶŐ ƌŽĂƚŝĂ ĂŶĚ ^ĞƌďŝĂ͕ ĐŽŶŶĞĐƚŝŶŐ ƚŚĞ ƌŽĂƚŝĂŶ ŐĂƐ ƚƌĂŶƐŵŝƐƐŝŽŶ ƐLJƐƚĞŵ ƚŽ ƚŚĞ ^ĞƌďŝĂŶ ŐĂƐ ƚƌĂŶƐŵŝƐƐŝŽŶ ƐLJƐƚĞŵ ^ůŽďŽĚŶŝĐĂ Ͳ ^ŽƚŝŶ ; ƌŽĂƚŝĂͿ Ͳ ĂēŬŽ EŽǀŽ ^ĞůŽ ;^ĞƌďŝĂͿ
EXPECTED BENEFITS
DĂƌŬĞƚ ŝŶƚĞŐƌĂƚŝŽŶ͕ ZĞǀĞƌƐĞ &ůŽǁƐ͕ ŝǀĞƌƐŝĨŝĐĂƚŝŽŶ ŽĨ ƌŽƵƚĞƐ͕ EͲϭ ZĞŐŝŽŶĂů ;&Žƌ ^ĞƌďŝĂͿ͕ ĂĐŬͲƵƉ ĨŽƌ ƌĞŶĞǁĂďůĞƐ͕ /ƚ ǁŝůů ďĞ ŶĞǁ ĞŶƚƌLJ ƉŽŝŶƚ ĂŶĚ ƚƌĂŶƐŵŝƐƐŝŽŶ ƌŽƵƚĞ ĨŽƌ ƚŚĞ ŶĞĞĚƐ ŽĨ ^ĞƌďŝĂ͕
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
| 40
GRIP Central Eastern Europe 2014–2023 Annex B
CROATIA
TRA-N-086
,QWHUFRQQHFWLRQ &URDWLD 6ORYHQLD %RVLOMHYR .DUORYDF /XþNR =DERN 5RJDWHF
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter Operator TEN-E Project ?
Plinacro Ltd Plinacro Ltd
Not part of TEN-E Yes
Interested by PCI ? IGAs
None
Web Link
ǁǁǁ͘ƉůŝŶĂĐƌŽ͘Śƌ
WůŝŶĂĐƌŽ ;ϭϬϬйͿ
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Applied for Exemption ? Exemption granted ? Considered TPA Regime Considered Tariff Regime
End of permitting phase
# of Pipelines, nodes, CS Total Pipeline Length (km)
Regulated Regulated
5 +296,00
FID Construction Commissioning Last completed Phase :
2017
Total CS Power (MW) Expected Load Factor
No
No
2018
+0,90
% Exemption in entry direction % Exemption in exit direction
0%
Planned
0%
| 41
GRIP Central Eastern Europe 2014–2023 Annex B
CROATIA
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone
To Zone
Modelled Direction No exit Yes entry
Rogatec
165,00 165,00
Hub Slovenia
Hub Croatia
DESCRIPTION OF THE PROJECT
hƉŐƌĂĚŝŶŐ ŽĨ ƚŚĞ ĞdžŝƐƚŝŶŐ ŝŶƚĞƌĐŽŶŶĞĐƚŝŽŶ ƌŽĂƚŝĂͬ^ůŽǀĞŶŝĂ
EXPECTED BENEFITS
^ĞĐƵƌŝƚLJ ŽĨ ^ƵƉƉůLJ͕ DĂƌŬĞƚ ŝŶƚĞŐƌĂƚŝŽŶ ;ĐƌŽĂƚŝĂŶ ŵĂƌŬĞƚ ĂŶĚ ƚŚĞ ŵĂƌŬĞƚƐ ŝŶ ƌĞŐŝŽŶͿ͕ ZĞǀĞƌƐĞ &ůŽǁƐ͕ ŝǀĞƌƐŝĨŝĐĂƚŝŽŶ ŽĨ ƐŽƵƌĐĞƐ͕ ŝǀĞƌƐŝĨŝĐĂƚŝŽŶ ŽĨ ƌŽƵƚĞƐ͕ EͲϭ EĂƚŝŽŶĂů ;ĨŽƌ ƌŽĂƚŝĂ ĂŶĚ ^ůŽǀĞŶŝĂͿ͕ EͲϭ ZĞŐŝŽŶĂů͕ ĂĐŬͲƵƉ ĨŽƌ ƌĞŶĞǁĂďůĞƐ͕ /ƚ ǁŝůů ďĞ ƐŝŐŶŝĨŝĐĂŶƚůLJ ŝŶĐƌĞĂƐĞ ƚŚĞ ĐĂƉĂĐŝƚLJ ŽĨ ƚŚĞ ŝŶƚĞƌĐŽŶŶĞĐƚŝŽŶ ŽĨ ƚŚĞ ƌŽĂƚŝĂŶ ĂŶĚ ^ůŽǀĞŶŝĂŶ ŐĂƐ ƚƌĂŶƐŵŝƐƐŝŽŶ ƐLJƐƚĞŵƐ ŝŶ ƚŚŝƐ ĚŝƌĞĐƚŝŽŶ͘ /ƚ ǁŝůů ŝŶĐƌĞĂƐĞ ƚŚĞ ĐĂƉĂĐŝƚLJ ĂůŽŶŐ ƚŚĞ ƌŽƵƚĞ͕ ƉƌŽǀŝĚĞ ĞŶŚĂŶĐĞĚ ĂĐĐĞƐƐ ƚŽ ĂƵŵŐĂƌƚĞŶ ĂŶĚ /ƚĂůŝĞŶ ŐĂƐ ŵĂƌŬĞƚ͕͘
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
| 42
GRIP Central Eastern Europe 2014–2023 Annex B
CROATIA
TRA-N-083
,QWHUQDWLRQDO 3LSHOLQH 2PLãDOM &DVDO %RUVHWWL
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter Operator TEN-E Project ?
Plinacro Ltd Plinacro Ltd
Not part of TEN-E Yes
Interested by PCI ? IGAs
None
Italian section, tbd (100%)
Croatian section, Plinacro (100%)
Web Link
www.plinacro.hr
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Considered TPA Regime Considered Tariff Regime Applied for Exemption ? Exemption granted ?
End of permitting phase
# of Pipelines, nodes, CS Total Pipeline Length (km)
2 +220.00
Regulated Regulated
FID Construction Commissioning Last completed Phase :
Total CS Power (MW) Expected Load Factor
No
No
2027
+0.90
% Exemption in entry direction % Exemption in exit direction
0%
Planned
0%
| 43
GRIP Central Eastern Europe 2014–2023 Annex B
CROATIA
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone Hub Italia Hub Croatia
To Zone
Modelled Direction No entry No exit
Casalborsetti
506.00 506.00
Hub Italia Hub Croatia
DESCRIPTION OF THE PROJECT
Covering the territory from the gas node Omišalj on the island of Krk (Croatian Gas Transmission System) via Adriatic Sea to Casal Borsetti (Italian Gas Transmission System)
EXPECTED BENEFITS
Security of Supply, Market integration, Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (For Croatia), N-1 Regional, Back-up for renewables, It will be new cross border transmission between Croatia and Italy; fits in the idea of Adriatic Gas Ring,
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
| 44
GRIP Central Eastern Europe 2014–2023 Annex B
CROATIA
/1* 1
/1*59
1RQ ),'
LNG Terminal
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter Operator TEN-E Project ?
Not part of TEN-E Yes Plinacro Ltd LNG Hrvatska d.o.o.
Interested by PCI ? IGAs
None
Web Link
Plinacro (100%)
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Applied for Exemption ? Exemption granted ? Considered TPA Regime Considered Tariff Regime
End of permitting phase
Regasification facility Expected volume (bcm/y) Total CS Power (MW) Send-out (mcm/d)
Not applicable Not applicable
LNG RV Croatia +2,00
FID Construction Commissioning Last completed Phase :
No
No
2017
+5,50
Ship size (m3) Reloading ability ?
% Exemption in entry direction % Exemption in exit direction
0%
Planned
0%
No
| 45
GRIP Central Eastern Europe 2014–2023 Annex B
CROATIA
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone
To Zone
Modelled Direction Yes exit
LNG RV (Regasification Vessel) to Croatia
60,50
LNG Terminals Croatia
Hub Croatia
DESCRIPTION OF THE PROJECT
dŚĞ >E' Zs ǁŝůů ďĞ ƐŝƚƵĂƚĞĚ ŝŶ KŵŝƓĂůũ ŽŶ ƚŚĞ ŝƐůĂŶĚ ŽĨ <ƌŬ͕ ZĞƉƵďůŝĐ ŽĨ ƌŽĂƚŝĂ͘ /ƚ ŝƐ ĐŽŶƐŝĚĞƌĞĚ Ă ƉĂƌƚ ŽĨ ƚŚĞ ŶĞƌŐLJ ŽŵŵƵŶŝƚLJ 'ĂƐ ZŝŶŐ͕ ǁŚŝĐŚ ŝƐ ƚŚĞ ĐŽŶĐĞƉƚ ŽĨ ŐĂƐŝĨŝĐĂƚŝŽŶ ĨŽƌ ƚŚĞ ĞŶƚŝƌĞ ƌĞŐŝŽŶ͕ ƉƌŽƉŽƐĞĚ ďLJ ƚŚĞ t ^ƚƵĚLJ ĂŶĚ ĂĐĐĞƉƚĞĚ ďLJ ƚŚĞ 'ĂƐ &ŽƌĂ ŽĨ ƚŚĞ ŶĞƌŐLJ ŽŵŵƵŶŝƚLJ͘
EXPECTED BENEFITS
Security of Supply, Market integration (Croatia, markets of Central and Western Europe (Austria, Slovenia, Hungary, Slovakia, Check Republic) as well as the Balkan countries (Serbia, B&H, DŽŶƚĞŶĞŐƌŽ͙ͿͿ͕ Diversification of sources, Diversification of routes, N-1 National (for Croatia), N-1 Regional, Back-up for renewables,
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
| 46
GRIP Central Eastern Europe 2014–2023 Annex B
CROATIA
TRA-N-090
/1* HYDFXDWLRQ SLSHOLQH 2PLãDOM =ORELQ &URDWLD 5XSD 6ORYHQLD
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter Operator TEN-E Project ?
Plinacro Ltd Plinacro Ltd
Not part of TEN-E Yes
Interested by PCI ? IGAs
:ĞůƓĂŶĞ ;ŶĂŵĞ ŽĨ ƚŚĞ ĐŽŶŶĞĐƚŝŽŶ ƉŽŝŶƚ ŽŶ ^ůŽǀĞŶŝĂŶ ďŽƌĚĞƌͿͲ
1
KŵŝƓĂůũ Ͳ ůŽďŝŶ Ͳ ZƵƉĂ ;,ZͿ Ͳ :ĞůƓĂŶĞ ;^ůŽǀĞŶŝĂŶ ďŽƌĚĞƌͿ͕ WůŝŶĂĐƌŽ ;ϭϬϬйͿ
<ĂůĐĞ͕ WůŝŶŽǀŽĚŝ ;^ůŽǀĞŶŝĂŶ d^KͿ ;ϭϬϬйͿ
Web Link
ǁǁǁ͘ƉůŝŶĂĐƌŽ͘Śƌ
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Considered TPA Regime Considered Tariff Regime Applied for Exemption ? Exemption granted ?
End of permitting phase
# of Pipelines, nodes, CS Total Pipeline Length (km)
3 +103.60
Regulated Regulated
FID Construction Commissioning Last completed Phase :
Total CS Power (MW) Expected Load Factor
No
2017 2018
No
+0.90
% Exemption in entry direction % Exemption in exit direction
0%
Planned
0%
| 47
GRIP Central Eastern Europe 2014–2023 Annex B
Made with FlippingBook