ENTSOG GRIP CEE 2014-2023 / Annex B : Infrastructure Projects
BULGARIA
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone
To Zone
Modelled Direction Yes entry
South Stream into Bulgaria (BG)
62,10
South Stream (Russia)
Hub Bulgaria (NGTS)
DESCRIPTION OF THE PROJECT
Second stage of the South Stream interconnection to the Bulgarian network, as understood by ENTSOG based on e-mail exchange.
EXPECTED BENEFITS
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
| 27
GRIP Central Eastern Europe 2014–2023 Annex B
Made with FlippingBook