ENTSOG GRIP CEE 2014-2023 / Annex B : Infrastructure Projects
GERMANY
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone
To Zone
Modelled Direction Yes exit Yes exit
Hub Germany (GASPOOL) Hub Germany (GASPOOL)
Gernsheim Eynatten 1 (BE) // Lichtenbusch / Raeren (DE)
105,60 30,00
Hub Belgium (H-Zone) Hub Germany (NCG)
DESCRIPTION OF THE PROJECT
None
EXPECTED BENEFITS
Market integration (GASPOOL / NCG (Gernsheim)), Diversification of sources,
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
| 64
GRIP Central Eastern Europe 2014–2023 Annex B
Made with FlippingBook