Previous Page  12 / 64 Next Page
Information
Show Menu
Previous Page 12 / 64 Next Page
Page Background

10

MODERN MINING

November 2015

MINING News

True Gold Mining Inc, listed on the TSX-V,

reports that mining has commenced at

the Goulagou II (GGII) deposit at the Karma

goldmine in Burkina Faso. The GGII deposit

is the first of six deposits that will be mined

over an 11,5-year period. The company

remains on track for gold production at the

end of Q1, 2016.

The GGII deposit has reserves of 273 000

leachable ounces of gold (contained in

7,6 Mt at 1,12 g/t gold) and will be mined

during the first two years of production.

“As we transition into gold production

over the next few months, our team is

increasingly focused on operational readi­

ness,” states Christian Milau, President and

CEO of True Gold. “Karma will produce

approximately 120 000 ounces of gold per

True Gold on track for gold production at Karma

year during our first five years at the lowest

quartile of cash costs, laying the founda­

tion for True Gold to become a mid-tier

producer.”

Karma mine construction is rapidly

progressing with nearly 1 000 employees

and contractors active on site. Overall, the

project is approximately 73 % complete

A recent view of the Karma project, which will produce approximately 120 000 ounces a year of gold in its first

five years of operation (photo: True Gold).

and is funded through construction to

production.

The mine fleet has been deployed to

GGII after completing significant exca­

vation of bulk earthworks at the mine’s

processing and storage ponds. Operators

of the mining equipment are experienced

from the excavation of the processing and

storage ponds, and are now trained and

ready for production work.

Excavation of Cells 1, 2 and 3 of the

heap leach pad is substantially complete.

Civil construction is ahead of schedule. The

raw water and pregnant leach ponds are in

place and the 4 km pipeline from the bar­

rage to the site is now being used to pump

water to these ponds, ensuring the process­

ing plant start-up requirements are met.

At the plant site, construction of the cya­

nide mixing area is complete with all civils

and tanks in place. The hard rock crusher

has been commissioned and is producing

aggregate for the drainage layer of the

heap leach pads. The ADR building struc­

tural steel is 100 % complete. Installation of

siding and roofing is progressing quickly,

as well as piping and electrical.

Kalongwe copper project granted mining licence

ASX-listed Regal Resources says that it has

been informed by KalongweMining SA (KM)

– in which it has a 30 % interest – that the

DRC Minister of Mines, Martin Kabwelulu,

has signed an‘Arrêté Ministériel’granting an

exploitation (mining) licence in accordance

with the DRC Mining Code.

The licence granted to KM covers the

entire KM permit, an area of approximately

8 km

2

. It is valid for an initial term of 30 years

and can be renewed for additional periods

of 15 years.

Comments David Young, Regal’s MD:

“The granting of a mining licence repre­

sents a major milestone for the Kalongwe

Mining Joint Venture and is the culmina­

tion of the efforts by the three JV partners

GICC, Regal and Traxys. The licence pro­

vides an additional level of confidence that

a mining operation will be developed at

Kalongwe and further de-risks the project.

A DFS has commenced and recent metal­

lurgical testwork results are expected to

have a positive impact on the financial

parameters for the study.”

The Kalongwe project is located 45 km

from Kolwezi (and 15 km from Ivanhoe’s

Kamoa discovery) in Katanga and hosts

a near-surface oxide JORC resource of

302 000 t contained copper and 42 000 t

contained cobalt, with an average copper

grade of 2,71 % Cu.

Australia’s Resolute Mining has executed

an agreement to divest the company’s

residual interests and assets in Tanzania.

The divestment decision follows the clo­

sure of Resolute’s Golden Pride mine in late

2013 and the subsequent completion of

Resolute Mining wraps up in Tanzania

the decommissioning and rehabilitation of

all elements of the company’s operations.

As agreed with the Government of

Tanzania, the mine site and all remaining

infrastructure was formally handed over

to the Madini Institute at a ceremony on

12 December 2014 to enable the establish­

ment of a mining institute of learning.

Resolute began construction of the

Golden Pride mine, the first modern gold

mine in Tanzania, in 1997 and operated the

mine for 15 years, successfully producing

more than 2,2 million ounces of gold. MD

and CEO John Welborn says the compa­

ny’s exit from Tanzania has closed a proud

chapter in Resolute’s history.

“Golden Pride was a strong driver of

value for Resolute and demonstrates the

company’s ability to profit from our expe­

rience in Africa. Resolute is a responsible

and experienced owner and operator of

quality gold mines and we are increasingly

recognised, particularly in Africa, as a part­

ner of choice for governments and local

communities,” he says.