Functional Safety Management within the constraints of a real-life major project

Ensure HAZOP is properly documented with consideration of later SIL

assessment activities.

Consider in design likely high risk (high SIL) areas to avoid frequent testing that

impacts operations, e.g. redundancy of valves, to avoid later design changes.

Equipment and package specifications must consider any potential FS

requirements to avoid later disputes with suppliers. Note the new and more

onerous requirements for suppliers related to their FS management.

Ensure design change management procedures reflect FS requirements at the

correct life cycle stage

11

Project activities