Periodic Proof Testing (PT) is critical to provide assurance that the Safety

Instrument Function (SIF) provides the required risk reduction throughout

its Operational lifecycle.

The purpose of the PT is to detect dangerous undetected failures that

cannot be detected by the systems diagnostics.

However, not all failures can be detected by diagnostics and PT and may

only be identified during overhaul or when a demand is actually placed on

the SIF.

The fraction of undetected dangerous failures detected by the proof test is

referred to as the proof test coverage factor

(

C

PT

)

.

This presentation and the associated paper aims to identify how the C

PT

can be determined; the impact it has on the PFD

AVG

; where this information

can be located and how it can be applied in industry.

Introduction