Central Eastern Europe GRIP 2017

INVESTMENT PROJECTS COMMISSIONED AFTER THE PUBLICATION

OF THE CEE GRIP 2014–2023

PROJECT PROMOTER PROJECT NAME

CODE

Bulgartransgaz EAD

Romania–Bulgaria Interconnection (EEPR-2009-INTg-RO-BG)

TRA-F-57 

1)

eustream, a.s.

Slovakia–Hungary interconnection

TRA-F-016

Exit Capacity Budince

TRA-F-1047 

2)

GASCADE

Gastransport GmbH

Installing a reverse flow in Mallnow

TRA-F-292

Installation of Nord Stream onshore project

TRA-F-289

Extension of GASCADE grid in the context of the Nord Stream (on-shore) project

TRA-N-249

Gasunie Deutschland

Transport Services

GmbH

Extension of existing gas transmission capacity in the direction to Denmark – 1. Step TRA-F-231

Extension of existing gas transmission capacity in the direction to Denmark – 2. Step TRA-N-232

GAZ-SYSTEM S.A.

Physical reverse flow on the metering station in Mallnow

TRA-F-326

Upgrade of gas infrastructure in northern and central Poland

TRA-F-248

Upgrade of the entry points in Włocławek on the Yamal-Europe pipeline

TRA-N-276

LNG terminal in Świnoujście

LNG-F-246

Increase of reverse capacity at Mallnow interconnection point

TRA-F-893

Physical reverse capacity at Lasów interconnection point

TRA-F-897

Magyar Gáz Tranzit ZRt.

Slovak-Hungarian interconnector (Vecsés–Szada–Balassagyarmat)

TRA-F-148

Plinovodi d.o.o.

CS Kidričevo (3

rd

unit 3.5 MW)

TRA-F-096

M2/1 Trojane – Vodice

TRA-F-097

M2/1 Rogaška Slatina – Trojane

TRA-F-104

MRS Šempeter – Reconstruction

TRA-F-110

SNTGN Transgaz S.A.

RO–BG Interconnection

TRA-F-029

terranets bw GmbH

Nordschwarzwaldleitung

TRA-N-228

1) This project was not in the CEE GRIP 2014–2023, but it was commissioned in November 2016.

2) This project was not in the CEE GRIP 2014–2023, but it was commissioned by the end of 2016

Table 2.1:

Investment projects commissioned after the publication of the CEE GRIP 2014 – 2023

The table below summarises investment projects that were included in the CEE

GRIP 2014–2023 and have been commissioned since the release of the last CEE

GRIP report in May 2014.