August 2016
7-4
City of Morgan Hill
2015 Urban Water Management Plan
These potential water use increases can be offset, in part, by increasing water conservation
measures.
The supply available to the City during the various hydrologic water years, summarized in
Table
7-1
, is assumed to be equal to the estimated rate of natural groundwater recharge, recycled water
consumption for users in the City of Gilroy, and the raw and surface water deliveries managed
and negotiated by SCVWD. The SCVWD 2015 UWMP estimates the percent of normal year
supply available during the single dry and multiple dry water years; these percentages are applied
to rate of recharge during the normal water year to determine the available supply during the
single dry and multiple dry water years.
The demand projections for the various hydrologic water years are summarized on the following
pages in
Table 7-2
,
Table 7-3
, and
Table 7-4
. These tables include the total projected water
demands through 2040, and estimates for total estimated water supply based on the hydrologic
water years. A water budget, as derived from SCVWD groundwater planning estimates, has been
included for the Llagas subbasin and Coyote Valley subarea respectively on
Table 7-2A
and
Table 7-2B
. These tables document the estimated total supply and demand during normal water
years.
Table 7-2 Normal Year Supply and Demand Comparison
2020
2025
2030
2035
2040
(AF)
(AF)
(AF)
(AF)
(AF)
Supply
63,900 67,800 71,500 73,300 73,400
Demand
61,765 65,542 69,468 72,811 74,068
Difference
2,135 2,258 2,032
489
-668