Simon Storage – ISCo West
Area ‘G’ Gas Detection – I&E Scope of Work
P & I Design Ltd
DOCUMENT NO: SI051001_INS
2 Reed Street, Thornaby, UK, TS17 7AF
ISSUE: A DATE: 08/04/11
Tel: + 44 (0)1642 617444
PAGE 5 OF 12
Fax: + 44 (0)1642 616447
www.pidesign.co.uk2
GENERAL REQUIREMENTS
Detailed in document SI002001.INS - Standard Specification for Instrument & Electrical
Installation Section 2 with the following additional information -
A “For Construction” package will be issued prior to contract. Modifications from the “for
Tender” package will be highlighted.
The contractor is to supply details of labour usage to complete the installation on
programme. The contractor shall also supply day rate costs.
Normal site working hours 8AM to 6PM Monday to Friday.