Previous Page  40 / 48 Next Page
Information
Show Menu
Previous Page 40 / 48 Next Page
Page Background

CAPITAL EQUIPMENT NEWS

MARCH 2016

38

TRANSPORT & LOGISTICS

L

ocally based international heavy-lift,

specialised transport and plant instal-

lation company, Vanguard has been

awarded the transport and crane erection

contract for the Nojoli Wind Farm near

Cookhouse in the Eastern Cape, once again

showcasing its experience in this sector

and its specialised engineering solutions.

The Nojoli project comprises 44 Vestas

V100 2 MW wind turbine generators, which

have the capacity to generate more than

275 GWh per year or enough for 86 000

South African households.

“In recent years we have transported and

erected over 160 turbines at wind farms

around South Africa,” said project and me-

chanical engineer Robbie Boshoff.

The company’s contract commenced with

discharging the vessel in December 2015

at the Port of Ngqura near Port Elizabeth,

and storage at the port. “The team on this

tight-deadline project had an early start to

the year, arriving back to discharge a sec-

ond vessel on 2 January 2016 with further

vessels to be discharged throughout the

project.”

According to Boshoff, the contract will run

until 23 June 2016, and involves not only

the discharge and storage at the port, but

also specialised transportation of all com-

ponents to site, about three and a half hours

away, followed by the erection of the tur-

bines utilising Vanguard’s GTK1100 crane.

A fleet of extendable and multi-axle trailers

transports the components, which include

nacelles weighing 72 tonnes, hubs of 21

tonnes, and turbine blades of 50 metres in

length.

“Among the challenges to be managed on

this route to site is a mountain pass with

very narrow turns,” said Boshoff. “We work

with the traffic authorities to close off the

pass entirely, so that our extendable trailers

can safely use the whole road to manoeuvre

the blades through the turns.”

On site, the GTK crane is assisted by a

dedicated and specialised team, including

two qualified Red Seal riggers, who lead

the team to assemble and break down the

crane, so that it can be moved and posi-

tioned for the next turbine – each process

taking around 10 hours. “Another team

pre-populates the handstands with the

components in advance to ensure that no

delays occur with the main build,” he said.

With every aspect of the job, detailed meth-

od and risk assessments are done, includ-

ing environmental assessments.

Once operational, Nojoli Wind Farm’s en-

vironmentally-friendly electricity supply

will save the atmosphere from more than

251 000 tonnes of carbon dioxide each year,

which would have come from coal-powered

stations.

The wind farm is being constructed by Enel

Green Power, which has about 740 plants

operating in 15 countries in Europe, the

Americas and Africa; EGP’s total installed

capacity is 9 600 MW from a range of

sources including wind, solar, hydroelectric,

geothermal and biomass.

b

VANGUARD AT WORK

with wind turbines at Nojoli