Ranked Capital Projects
2017-2021 FINANCIAL PLAN
NORTH SURREY ARENA REPLACMEENT
$52,000,000
The North Surrey Arena contains 2 sheets of ice; one of the sheets was built in 1966 and
is at the end of its useful life. To ensure that the users of that arena are not displaced due
to a facility failure, in 2016 the City started to plan and build the replacement of the 2
sheets prior to closing the existing arena, an additional sheet of ice will be added to
meet the growing demand for ice sports and dry floor use in the City resulting in a 3
sheet sports complex in South Westminster. The 2017 contribution to this multi-year
project is $9,250.000.
OPERATING IMPACT: The 2017 – 2021 Financial Plan includes an additional $75,000 in
operating costs for the implementation and monitoring of this program.
PERFORMING ARTS CENTRE
$10,750,000
To further complement the existing Surrey Arts Centre’s 400 seat theatre and City Hall’s
Centre Stage 200 seat theatre, in 2016 a new performing arts space is planned in the
City. Given the City’s growth and large geographic, there is demand for an additional
performing arts space. This budget will support critical land acquisition. The 2017
contribution to this multi-year project is $500,000.
OPERATING IMPACT: The 2017 – 2021 Financial Plan includes an additional $56,000 in
operating costs for the implementation and monitoring of this program.
RCMP SPACE RENOVATIONS AT OLD CITY HALL SITE
$13,900,000
The former City Hall is being upgraded to accommodate up to 574 (Members) in an
RCMP Detachment expansion. Staff will occupy the south tower and the main floor of
the west wing. Interior renovations, system updates and improvements to the parking
compound comprise the bulk of the expansion, which will be completed in early 2017.
Phase Two of this project, renovations to Surrey RCMP Main Detachment will begin
immediately following occupation of former City Hall and is expected to be completed
by the end of 2017. The 2017 contribution to this multi-year project is $4,660,000.
OPERATING IMPACT: The 2017 – 2021 Financial Plan includes an additional $430,000 in
operating costs for the implementation and monitoring of this program.