px Limited, Bramhall Terminal – Functional Safety Committee

Minutes of Meeting February 2017

P & I Design Ltd

DOCUMENT NO: SC021008_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: B DATE: 30.03.17

Tel: + 44 (0)1642 617444

PAGE 5 OF 22

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

No.

Action

Action By

Status

24 It was noted that no modifications have been carried out since the previous

meeting. However some Pilz relays has been changed out (like for like)

and a report from Pilz is outstanding. The analysis and approval

documentation is to be updated following the next test. Chase report from

Pilz. June 2014 PILZ have not (and will not) issued a report as it is a safe

failure. ACTION considered as complete. PILZ to be contacted outside

this meeting.

D. Faulkner

Closed

Date

Action History

28/10/13

17/06/14

16/02/16

14/02/17

Ongoing

Ongoing discussions with Pilz, PILZ have not (and will not) issued a report as it is a safe

failure. Action considered as Complete

Action reopened, design change to be considered. Omron Relays for information outputs

as replacements for Pilz S11 relays.

Design complete and relays changed over in 2016.

No.

Action

Action By

Status

25

Environment Agency and HSE have visited the site in June 2014.

ACTION S.M.

S. Milward

Complete

Date

Action History

17/06/14

15/01/15

16/02/16

Actions, recommendations and comments from these meetings will be circulated to the

Functional Safety Committee.

Inspection reports reviewed briefly at the meeting. Actions captured by terminal action

tracker.

No CA inspection carried out in the last 12 months.

No.

Action

Action By

Status

26

There is dedicated contractor support for local electrical and

instrumentation issues, including the Safety Instrumented Systems. There

is no back-up for this cover and electrical drawings may not be up to date.

Knowledge base and cover to be considered.

S. Milward

Ongoing

Date

Action History

15/01/15

16/02/16

14/02/17

30/03/17

Methods of addressing this weakness have been considered and none are seen as

particularly viable. Documentation to be confirmed as complete and up to date.

Extra support has now been identified and documentation to be upgraded. IS Calculations

need to be provided as per DSEAR loop sheets required as part of documentation upgrade.

IS calculations and loop sheets now completed.

Contractors are now being introduced to site operations and maintenance to gain site

knowledge.

A proposal for the recruitment of an electrical technician was submitted to P66 in 2016,

however this has now been overtaken by the imminent transition to CLH. Future

arrangements are TBC