Background Image
Table of Contents Table of Contents
Previous Page  47 / 68 Next Page
Information
Show Menu
Previous Page 47 / 68 Next Page
Page Background

October 2015

T

he main building contractor,

BUA Africa Properties con-

tracted Gauteng Piling to pro-

vide 100 auger piles to an average

depth of 13 m, which serves as the

foundation for the Kagiso residential

development in Margaret Avenue,

Kempton Park.

Gauteng Piling Site Manager, Rof-

hiwa Tshivhinda says that the auger

piles covered an area of 3 000m². It

took five weeks to install the piles

after the existing structure had been

demolished and the site cleared.

“A multi-storey building of this

nature, towers over neighbouring

structures and requires exceptionally

strong piling to meet the high struc-

tural bending and horizontal forces.

The specifications included two lift

shafts on either side of the apartment

block would act as shear walls to

stabilise the entire building. Gauteng

Piling used 18 piles underneath the

lift shafts by inserting five additional

micro-piles (eg piles-within-piles) to

support and strengthen the founda-

tions. The micro-piles were drilled

through Cross Hole Sonic Logging

(CHSL) tubes and extended into the

pile cap.

“Exceptionally robust 36 mm

Thread Bar steel rods (TB950) were

then inserted by the overhead crane

into the micro-pile anchors for ad-

ditional stability. Each micro-pile

was inserted to a depth of 6 m below

the pile toe and were grouted at

40Mpa at a final depth of 20 m,” said

Tshivhinda.

All of these relatively voluminous

and intricate components were

housed in specially-designed 13 m

long steel cages, with a diameter of

800 mm and weight of 1.8 tons each.

The tensile strength of these cages

for the lift shaft piles are almost four

times stronger than the steel used

for the rest of the piling cages on the

project. To accommodate the wide

cages, 900 mm diameter piles were

drilled using two Williams diggers.

Prior Gauteng Piling’s contract,

the main contractor commissioned a

Deep foundations for

11-storey residential block

company to handle the geotechnical

investigations. This resulted in four

large diameter auger trial holes being

drilled in a grid pattern, spaced 30

m apart. “The holes were drilled to

refusal on very soft, to soft, basaltic

lava rock and showed that the maxi-

mum depths that could be reached

before refusal were from 9.1 m to

13m. Groundwater was encountered

at a depth of 11 m and therefore

Cement & Concrete

Leading piling contractor, Gauteng Piling, provided intricate and

robust foundation piling for the construction of a new 11-storey 240

unit residential apartment block in Kempton Park’s

Central Business District.

Gauteng Piling had to employ the

drill-and-cast method of piling for the

entire contract.

This form of piling calls for a con-

crete truck on standby next to the

drill rig so that concrete can be cast

immediately after the drilling flights

are extracted to the surface.This pre-

vents water ingress and collapse of

the piles,” said Tshivhinda.

Gauteng Piling, established by

Nico Mass, a leading Master Builders

SA industry stalwart and MBA North

member, will celebrate its 20th anni-

versary next year. Gauteng Piling has

in the past 19 years completed over

1 500 projects and is now one of the

major players in the piling industry.