Background Image
Table of Contents Table of Contents
Previous Page  19 / 40 Next Page
Information
Show Menu
Previous Page 19 / 40 Next Page
Page Background

17

Chemical Technology • June 2015

Construction

The first works will be civil works in the form of base camps,

access roads, and laydown areas for materials. The Con-

struction Management teamwill act for and on behalf of the

owner and the team will usually consist of a Site Construc-

tion Manager an HSE Manager, a Quality Control Manager

and numerous Site Craft Supervisors and a site Planner.

Quality Management System

Construction quality systems usually follow the International

Standards Organisation (ISO) 9001:2008 format [7]. The

owners demand written documentation defining quality

requirements of every aspect of the new pipeline.

Scheduling of packages

Contractor personnel will maintain a status of the prog-

ress on the completion of package activities when overall

construction progress reaches the 50 % milestone. These

system handover packages will be used to track the comple-

tion of various construction, inspection, or mechanical

completion activities in order to be able to quickly determine

the completion status of any given system.

Punchlists

System punchlists will list items that are incomplete, not

in conformance with the construction documents, or that

require modification.

Contractor will sign-off and advise owner to verify that

the punchlist items have been completed in accordance

with the construction documents.

Handover /Mechanical completion

Handover is the sequence of events leading to transfer

of custody of a system from contractor to owner. It is the

demarcation between the construction phase and commis-

sioning/Start-up operations.

Pre-commissioning [8]

Pre-commissioning activities are associated withmaking the

system ready for operation and will include the following:

• De-watering of residual hydrostatic test water in the

pipeline

• Flushing and dry air blowing of above ground piping and

valve and pigging stations.

• Swabbing of pipeline

• Low pressure leak check (with air) for the above ground

section of the pipelines.

Commissioning procedure [9]

Instrument controls and interlocks are functional as per the

normal operating conditions.

Utilities

- Utilities such as power, UPS, water, air, instru-

ment air and HVAC will be checked.

Alarm systems

- Setting off alarms and their functioning

will be ensured.

Safety

- Identification of possible emergencies and pre-

paredness for its mitigation will be checked.

To clear the pipeline of metallic particles, magnetic clean-

ing will be carried out using a train of brush magnetic pigs.

An intelligent pigging survey will be carried out recording the

entire length in one single run. The report will include a de-

tailed description of the type, size and location of individual

mechanical defects. The repair of defects will be carried out

in accordance with that specified in IS 15663 (Part 1) [9].

The pipeline system needs to be rendered inert using

nitrogen.

The system will be considered to have been commis-

sioned successfully when the pipeline system has run suc-

cessfully for a minimum period of 72 h at stable operating

conditions and instrumentation/control systems, process

utilities and support systems taken on line. Commissioning

documentation records must be kept by the contractor.

Start-up/Runtest

Start-up begins when all system pre-commissioning and

commissioning are completed and accepted by the owner.

Performance guarantee

Contractor will guarantee the performance of all equipment

and material in his supply, based on the ability of the com-

plete system to be able to flow the design volume of gas, at

the design pressure to the discharge location

Challenges involved in constructing a

pipeline

There are a significant number of challenges in the construc-

tion of a pipeline [9], in particular:

• Sustaining the project with the number of resources

required over a long period of time

• Permission from local authorities and construction

notifications

• EIA assessment approvals, in particular wildlife conserva-

tion areas and mitigation plans

• Different sections of a pipeline will have particular issues,

eg, conservation areas

• Pipeline safety can have special conditions that have to

be agreed to as part of the EIA

• During construction, local authorities need to be kept

abreast of any issues that may arise

• Directional drilling at water or road crossings will be

necessary and can be difficult

• Safety in the design of the pipeline is paramount and

needs acute attention

• Trained artisans can be a problem to locate but proper

skills development is essential

• Multiple construction offices and laydown areas along

the pipeline are necessary

• Vendors need to be aware of the importance of materi-

als and equipment deliveries on time and at the right

location.

• Experienced project managers, engineering managers,

construction managers and craft supervisors are essen-

tial to enable a pipeline to be constructed under budget

and on time.

References

A list of references for this article is available from the editor

at

chemtech@crown.co.za.

PETROCHEMICALS

Advanced

Software

Platforms reduce

time spent on

routing the pipe-

line to weeks

rather than

months.