Background Image
Table of Contents Table of Contents
Previous Page  32 / 68 Next Page
Information
Show Menu
Previous Page 32 / 68 Next Page
Page Background

30

CONSTRUCTION WORLD

MAY

2015

PROJECTS AND CONTRACTS

Ednick Msweli, newly appointed head of eThekwini Water

and Sanitation (EWS) confirmed this week that the two

multi-million rand contracts that make up a portion of the

Northern Aqueduct Augmentation (NAA) are expected to be

complete in the fourth quarter this year.

This includes a 6 km section of the pipeline that begins at Duffs

Road and ends at the Phoenix 2 reservoir and a 22 km segment of

the pipeline that stretches from the Phoenix 2 Reservoir in Phoenix,

continues to Waterloo and then to Umhlanga with a feed to the

planned new Blackburn reservoir.

The current Northern Aqueduct has reached capacity on various

sections of the trunk mains as a result of growth in demand. As a

result, although there is sufficient water to meet current needs, there

is not sufficient network capacity to deliver it to areas that need it

most. Construction of the NAA will resolve this.

Msweli said that the NAA, which comprises seven individual

projects, would not be constructed in linear fashion. Segments in

areas of critical need will be put in place first.

He confirmed that, by the end of the year, the pipeline to the

Waterloo Reservoir will be complete. “This will alleviate the water

shortages and rationing currently being experienced in the Phoenix

and Waterloo areas. These areas currently receive water from

Hazelmere Dam which is low. We will be able to reroute water to

compensate for this.”

Martin Bright, project manager for the NAA, said that the actual

construction of these two contracts was complex with special meas-

ures being taken to accommodate residents, preserve environmen-

tally sensitive flora and rehabilitate excavation sites.

Although a large portion of the pipeline has been routed through

sugar cane fields, a critical portion does traverse busy residential

areas, crossing busy thoroughfares. He urged residents to be patient

as EWS worked to alleviate the

water shortages that are currently

causing concern.

He said motorists could expect

traffic interruptions over the

next two months along Phoenix

Highway. As the road is not wide,

construction has to extend into

the road.

Bright added that EWS had

already commissioned consult-

ants to undertake the Environ-

mental Impact Assessment and

design of the link from Reser-

voir Hills (also known as Durban

Heights) to Duffs Road. This will go

out to tender in early 2016.

Construction of the 30 month

long contract is expected to start

in mid-2016. This, too, will entail

an extremely complex construc-

tion process that involves excava-

tion and laying of a 1,2 m diameter

steel pipe along a route of approx-

imately 15 kms.

Phases of

AQUEDUCT

nearing completion

Construction of R250-million worth of

urgently needed bulk water infrastructure

in the northern part of the eThekwini

region is nearing completion.

>

Excavating the trench along which the 1,2 m diameter water pipe will be laid

to allow sufficient bulk water to supply the northern parts of Durban.

The bulk water pipe has been laid in

the excavated area in the centre of the

Phoenix Highway.