Background Image
Previous Page  39 / 108 Next Page
Basic version Information
Show Menu
Previous Page 39 / 108 Next Page
Page Background

January 2014

37

www.read-eurowire.com

News

Corporate

VSMC has completed the

shallow water-trenching

programme

for

the

London Array wind farm

project, having started

work at the site in 2009.

For VSMC, the London

Array project consisted

of

the

installation

and

burial

of

four

export cables and the

installation, burial and

termination

of

178

infield cables. VSMC set a

record by completing the

installation and burial of

216km of export cables

in 12 months and the

installation and testing of 202km of infield cables in just nine months.

VSMC was also contracted to trench 177km of infield cables on a challenging work

site with strong currents and areas that fall dry, requiring unconventional methods of

trenching.

CEO Arno van Poppel said: “The success of this project was down to the dedication and

commitment of the project team members, all of whom worked hard to ensure that the

project was completed safely and to a very high standard.”

VSMC – Netherlands

Website

:

www.vsmc.nl

Commission completed at Thornton Bank

The subsea transmission

link

connecting

one

of the largest offshore

wind farms in Europe

to the Belgian grid, the

Thornton Bank project,

has been successfully

commissioned by ABB.

The work, executed for

the

Belgian

company

C-Power

NV,

was

completed on schedule.

The transmission link is

part of an expansion of

the Thornton Bank wind

farm. In the first phase

of its development, six

wind turbines with a total capacity of 30MW were built and temporarily connected

to the mainland by ABB. The second and third phases of the project involved adding

48 wind turbines to the wind farm and connecting the complete wind farm, taking its

overall capacity to 325MW. The transformer station platform is 30km offshore in the

North Sea.

ABB was responsible for the system engineering, design, supply and commissioning

of the alternating current subsea cables, the land-based cable systems, the offshore

substation and the platform that houses it. The wind turbines are connected via

underwater medium-voltage cables to the offshore transformer station where the

voltage is boosted to 150kV and connected to the mainland grid.

The wind farm has a generating capacity of over 1,000 gigawatt-hours of electricity per

year, and by 2020 will contribute approximately seven per cent of Belgium’s targeted

renewable energy commitment.

ABB – Switzerland

Website

:

www.abb.com

End of Array work for VSMC

Cable laying for London Array site. Photograph courtesy of VSMC website

The subsea transmission link. Photograph courtesy and ©C-Power NV, T

D’Haenens