Nustar Terminals – Belfast Terminal

IHLA Safety Instrument System - Functional Safety Assessment

P & I Design Ltd

DOCUMENT NO: NU271001_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: F DATE: 30.06.17

Tel: + 44 (0)1642 617444

PAGE 69 OF 72

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

6

ACTIONS

Action

No.

Action

By

Expected

Completion

Completion

Date

1

PFD to be added in to the

LOPA calculation to confirm

suitability of risk reduction

Nustar

Terminals

End

October

2011

30/09/11

2

LOPA calculation is to be re-

worked to consider the

mitigated risk whilst the bund

liquid level detectors are not

installed.

Nustar

Terminals

End

October

2011

30/09/11

3

NuStar may decide to add to

the Functional Specification

details that are required within

a SRS, but not currently in the

Functional Specification.

Nustar

Terminals

End

October

2011

30/09/11

4

Provide a block diagram

showing functionality of the

various SIF’s

Nustar

Terminals

End

October

2011

30/09/11

5

Software or software validation

to be provided to complete

FSA

Nustar

Terminals

End

November

2011

End November

2011

6

Review of override control to

be assessed against PSLG

guidance

Nustar

Terminals

&

FSA

End

October

2011

30/09/11

7

NuStar to confirm how they

will provide management of

change now the system is

operational. Also include

unique document numbers to

documentation, at present, un-

numbered.

Nustar

Terminals

End

November

2011

April 2012

8

Review LOPA for the addition

of gasoline tank to tank

transfers. Still incomplete

Nustar

Terminals

End

November

2013

March 2015

9

Review of SIL Verification

document including check of

PFD and hardware fault

tolerance calculations.

P & I Design

Ltd

End

November

2011

End November

2011

10

Safety,

Operating

and

maintenance Procedures to be

reviewed.

FSA

07/09/11

30/09/11

11

Review of validation and

Testing plans and procedures.

FSA

07/09/11

30/09/11

12

Review training, maintenance

and operation procedures.

FSA

07/09/11

30/09/11