Table of Contents Table of Contents
Previous Page  77 / 488 Next Page
Information
Show Menu
Previous Page 77 / 488 Next Page
Page Background

68

Wiley IFRS: Practical Implementation Guide and Workbook

quest furnish details of the contract costs incurred to date by component. After submission of the

separate proposals, it was agreed that the split of the contract price of $ 100,000 would be in the ratio of

70% for construction of the new bridge and 30% for demolishing the existing bridge.

Required

Evaluate in light of the provisions of lAS 11 whether the contract for the construction of the new bridge

and the contract for demolishing the existing bridge should be segmented and treated as separate con–

tracts or be combined and treated as a single contract.

Solution

The two contracts should be

segmented

and treated as

separate contracts

because

• Separate proposals were submitted for the two contracts.

• The two contracts were negotiated separately.

• Costs and revenues of each contract can be identified separately.

3.2

Combining Contracts

3.2.1

A group of contracts, each with a single or even with different customers, shall be treated as

a

single contrac t

when

( I ) The group of contracts is negotiated as one single package;

(2) The contracts are so closely interrelated that they are effectively (Le.,

in substance)

part of

one project with one overall profit margin;

and

(3) The contracts are performed either concurrently or in continuous sequence.

Case Study 2

Facts

Universal Builders Inc. is well known for its expertise in building flyovers and maintaining these struc–

tures. Impressed with Universal' s track record, the local municipal authorities have invited them to sub–

mit a tender for a two-year contract to build a super flyover in the heart of the city (the largest in the re–

gion) and another tender for maintenance of the flyover for 10 years after completion of the construction.

Required

Evaluate whether these two contracts should be segmented or combined into one contract for the pur–

poses of lAS 11.

Solution

The two contracts should be

combined

and treated as a

single

contract

because

• The two contracts are very closely related to each other and, in fact, are part of a single contract

with an overall profit margin.

• The contracts have been negotiated as a single package.

• The contracts are performed in a continuous sequence.

3.2.2

Sometimes a contract may provide for the construction of an additional asset at the option

of the cu stomer or may be amended to include the construction of an additional asset. Under such

circumstances, the additional asset sha ll be treated as a separate contract when it differs signifi–

cantly from the asset(s) covered by the original contract

or

when the price is negotiated without

reg ard to the original contract price.

4. CONTRACT REVENUE

Contract rev enue

shall comprise the

initial price agreed

in the contract together with

variation s.

claims. and incentives

to the extent that it is probable that they will result in revenue

and

they are

capable of being

reliably measured .

4.1

Variations, Claims, and Incentives

Over time, the contract value may need to be amended either upward or downward , There can be a

significant degree of uncertainty and, therefore , estimation in asse ssing the contract value and

hence revenu e to be recognized in fin ancial statements. In all cases, the amount must be

reliably

measurable

and

realization is probable.

For example