Table of Contents Table of Contents
Previous Page  84 / 488 Next Page
Information
Show Menu
Previous Page 84 / 488 Next Page
Page Background

Chapter

8/

Construction Contracts (lA S II )

75

59.57% ($7, 148,000) of the contrac t price is recog nized as reve nue. Therefore, $7, 148,000 less cumula–

tive reven ue to year 2 of $1,265,000, or $5,883,000, is recog nized in year 3.

Note

(0 :

The subcontrac tor advance is dedu cted from the cost, as it is an advance for work to be exe –

cuted in yea r 4.

The percentage complete is based on the contract cos t of $12 million less the expec ted residual value of

the plant specifically acq uired for the contract plus the cos t of var iation. Th is is applied to the initial

contract value of $ 16 million, as the variation is not approved.

Year 4:

In year 4 the contract is complete and the full contrac t revenue of $ 17 mill ion (including the approved

var iation), less revenu e recogni zed in earlier years, is taken to the income statement.

Ove rall, the contract has revenu e of $ 17 million and costs of $ 12.6 15 million , earning a profit of

$4 ,385,000 ($2,0 16,000

+

$2,369,000). The loss in year I arises solely from the initial business trip,

which is not a con tract cost.

BALANCE SHEET

Year I

Year 2

Year 3

Year

4

Cumulative progress billings

$2,000,000 $7,000,000 $ 16,000,000

Variation

1,000,000

Total cumulative billings

2,000,000

7,000,000 17,000,000

Cumulative revenue recognized

$ 15,000

1,265,000

9,531,000 17,000,000

Disclosed as due from customers

15,000

2,53 1,000

Disclosed as due to customers

735,000

Disclosed as debtors (retention)

1,000,000

Contracts in progress

Costs incurred

15,000

1,265,000

7,515,000

nJa

Recognized profits

2,016,000

nJa