Previous Page  316 / 322 Next Page
Information
Show Menu
Previous Page 316 / 322 Next Page
Page Background

GAZETTE

JULY/AUGUST 1984

parties as to essential elements of the

alleged contract or contracts; (2) that it

was true to say that the contract or

contracts in issue would not be

enforceable by action unless, for the

purposes of Section 4 of the Sale of

Goods Act 1893, Tradax had accepted

part of the goods sold and actually

received the same, or there existed a

sufficient note or memorandum in

writing of the alleged contract or

contracts signed by I.G.B. or their agent

on their behalf. Gannon J. in the High

Court had drawn attention to a letter of

21 April 1978 written by the Secretary of

the I.G.B., who is also the Solicitor of the

latter, to Tradax purporting to repudiate

the alleged contract or contracts. The

Secretary had in the first paragraph of

this letter referred to the telex from

Tradax to I.G.B. dated 24 March 1978

"confirming the agreed terms of the

above-mentioned two contracts for

20,000 tonnes and 5,000 tonnes

respectively of Irish Feeding Barley and

which provided for payment by letter of

credit maturing on 1 May 1978". Gannon

J. had concluded that this letter coupled

with the telex of 24 March 1978

constituted a sufficient note or

memorandum of the contract(s) made on

23 March 1978. The majority of the

Supreme Court held that Gannon J. had

been correct in so holding. Griffin J. and

Henchy J. noted, furthermore, that even

if no sufficient note or memorandum had

come into existence the requirements of

the above-mentioned Section 4 had been

complied with because Tradax had

accepted and received part of the goods

amounting to 1,871 tonnes to the value of

£180,560; (3) that (McCarthy J.

dissenting) the contention put forward by

I.G.B. that the letter or letters of credit

ought to have been opened or established

at the latest, by the first day of the

contractual delivery period, (which in this

case was 1 April 1978), and that failure on

the part of Tradax in this regard resulted

in a breach of a fundamental term of the

contract entitling I.G.B. to repudiate

same, was to be rejected. O'Higgins C.J.

summarised the position thus:

"Although the persons negotiating the

terms of the contract were not familiar

with all the technicalities of

documentary credit, they were of one

mind that payment for the barley

purchased was to be by a letter of

credit for each lot, maturing on 1 May

1978.

This date was specified notwith-

standing that the shippingperiodfor the

shipments from New Ross was to run

from 1 April 1978 until 30 June 1978.

This case is therefore to be

distinguished from the run of cases of

sales based on payment by

documentary credit, where the

furnishing by the buyer of the

documentary credit is a precondition

of the shipping or delivery of the

goods by the seller."

The cases that had been cited by I.G.B.

in support of their argument were the

English cases of

Pavia and Company

S.P.A.

-v-

Thurman-Neilsen

[1952] Q.B.

84;

Sinason-Feicher Inter-American Grain

Corporation -v- Oilcakes and Oilseeds

Trading Co.

[1954] I.W.L.R. and

lan

Stach Ltd.

-v-

Baker Bosely Ltd.

[1958] I

All ER 542.0'Higgins C.J. opined that the

facts of the latter mentioned cases were

distinguishable from those of the present

case in that they all involved transactions

relating to international trade and

envisaged a payment machinery

operating over the whole of a shipping

period. The machinery for payment in the

present case, by way of contrast, operated

"on a single day with a single payment

and it is specifically recognised that it

cannot operate for the first month of the

delivery or shipping period". The

majority of the Supreme Court (McCarthy

J. dissenting) were not prepared to imply

a term that the letter of credit of the kind

actually opened by Tradax on 24 April

1978 ought to have been opened by 1

April (the commencement of the drawing

period). Not only would it be impracti-

cable for the parties to have agreed to

such a term but the subsequent actions

and conduct of I.G.B. and Tradax belied

the existence of a common intention that

such a term would implicitly form part of

the contractual arrangement which they

had entered into. The absence of such a

term did not, in any event, affect the

business efficacy of the transaction.

(The

Moorcock Case

[1889] 14 P.D. 64,

Shirlaw

-v-

Southern Foundries

[1939] 2 All ER

124,

Reigate

-v-

Union Manufacturing

Company (Ramsbottom)

[1918] I.K.B.

592, and

Ward

-v-

Spivack Ltd.

[1957]

L.R. 40 considered) Higgins C.J.

concluded that all that could be implied

into the contractual arrangement entered

into in the present case was that Mr.

Fitzpatrick, the Managing Director of

Tradax, "on behalf of his company

should take reasonable and proper steps

to finance the opening of a letter of credit

which would mature for payment of £2.4

million on 1 May. If he had been dilatory

in securing the transfer of funds to his

own company or otherwise acted as if the

contractual obligation would not be

honoured, there might have been grounds

for complaint by the Defendants".

I.G.B. were accordingly not justified in

cancelling their contract with Tradax on

21 April 1978.

McCarthy J., in his dissenting

judgment, considered that the crucial

factor in the circumstances was not May

1, the date of actual payment, but rather

that I.G.B. could look forward to such

payment on that date. If it were the

situation that the letter of credit was

merely to be opened on that date, and

opening requires notification to the

drawer, then this would mean that the

documentary credit could not in theory

have been drawn upon, at the start of

banking hours on that day. McCarthy J.,

consequently considered that, to the

extent that it be accepted that a valid

contract was entered into on 23 March

1978, a term necessarily implied therein

was that a letter of credit or letters of

credit . . . would be opened at a bank in

Ireland before the 1st day of drawing

down fromthe Edenderry Store or not

less than five days before the date of

arrival of a ship at New Ross for the f.o.b.

transaction, whichever date be the earlier.

McCarthy J. thus reached the conclusion

that as Tradax had failed to comply with

the above mentioned term which he

considered to be fundamental to the

contract, I.G.B. had been justified in

sending a letter on 21 April 1978

repudiating the earlier contract of 23

March 1978.

Tradax Ireland Limited

-v-

Irish Grain

Board Limited - Supreme Court, 18

November 1983 [1984] ILRM 471.

Edwina Dunn

PLANNING/PRESCRIPTIVE

RIGHTS/NUISANCE

SUMMARY OF DECISION

No intention to deliberately flout the

Planning Law in the erection of a

galvanised shed — no mandatory

injunction granted for the removal of the

structure — bona flde effort made by

Defendant to eliminate nuisance —

Plaintiff entitled to damages for nuisance

by noise and dust.

The Plaintiff was an elderly lady living

on her own in an attractive residence in

Navan. Her next-door-neighbour set

about erecting a structure along the line

of the dividing wall of the two back

gardens and within hours a massive

corrugated iron workshop was obscuring

the landscape at the back of her house.

The Plaintiff sought interlocutory relief

and by Order of the High Court, dated 8

October, 1979, an undertaking on the

part of the second-named Defendant,

Patrick Reilly, was given whereby he

undertook not to do any further building

work and not to use any of the new

buildings and premises for his joinery

business but remaining at liberty to use

the old buildings for such joinery

business. When proceedings were

commenced against him he applied for

permission to build and this Application

was rejected by the Local Urban District

Council but, on Appeal to An Bord

Pleanala, permission was granted subject

to conditions requiring the Defendant to

reduce the length of the building by 15'/

2

feet so as to set it back some distance from

the Plaintiffs premises and also requiring

steps to be taken to suppress the level of

dust and noise emanating from the

structure. One of the most effective ways

of complying with the requirements of An

Bord Pleanala with regard to noise and

dust was to substitute or superimpose

blockwork in place of or over the

XIV