Table of Contents Table of Contents
Previous Page  422 / 532 Next Page
Information
Show Menu
Previous Page 422 / 532 Next Page
Page Background

406

VOJTĚCH TRAPL

CYIL 5 ȍ2014Ȏ

the observance of commitments it has entered into with respect to the investments of the

investors of the other Contracting Party

.

15

It also asserted that “most or all of Pakistan’s

acts and omissions…qualify as breaches of the PSI Agreement as well as violations

of the BIT.”

16

While BIT claims and contract claims appear reasonably distinct in

principle, complexities arise on the ground, however, particularly in the present case,

each party claims that one tribunal (this Tribunal or the PSI Agreement arbitrator)

has jurisdiction over both types of claims which are alleged to co-exist.

17

During the hearing on the Respondent’s Objections to Jurisdiction, counsel

for the Claimant characterized this clause as an “elevator” or “mirror effect” clause,

which takes breaches of contract under municipal law and elevates them immediately

to the level of a breach of an international treaty.

18

The Arbitral Tribunal came to

the conclusion that a treaty interpreter must seek to give effect to the object and

purpose projected by that Article and by the BIT as a whole. Applying these familiar

norms of customary international law on treaty interpretation, the Arbitral Tribunal

did not find a convincing basis for accepting the Claimant’s contention that Article

11 of the BIT had the effect of entitling a Contracting Party’s investor, like SGS, to

“elevate” its claims grounded solely in a contract with another Contracting Party,

like the PSI Agreement, to claims grounded on the BIT, and accordingly to bring

such contract claims to this arbitration for resolution and decision.

19

Considering

the widely accepted principle that, under general international law, a violation of

a contract entered into by a State with an investor of another State is not, by itself,

a violation of international law, the Arbitral Tribunal further considered that the

legal consequences were so far-reaching in scope and so automatic and unqualified

and that there was not any clear and convincing evidence about shared intent of

the Contracting Parties to the Swiss-Pakistan Investment Protection Treaty in

incorporating Article 11 in the BIT.

20

The consequences of accepting the Claimant’s

reading of Article 11 would amount to incorporating by reference an unlimited

number of State contracts, as well as other municipal law instruments, setting out

State commitments, including unilateral commitments to an investor of the other

Contracting Party. Any alleged violation of those contracts and other instruments

would be treated as a breach of the BIT and the Claimant’s view of Article 11 tends

to make Articles 3 to 7 of the BIT substantially superfluous. There would be no

real need to demonstrate a violation of those substantive treaty standards if a simple

breach of contract, or of a municipal statute or regulation, by itself, would suffice to

constitute a treaty violation on the part of Contracting parties.

21

The Tribunal was

not saying that States may not agree with each other in a BIT and that henceforth

15

Ibid note 14. 97.

16

Ibid

at 84.

17

Ibid

at 97.

18

Ibid

at 163.

19

Ibid

at 165.

20

Ibid

at 167.

21

Ibid

at 168.