Estimated Time for Commissioning

It takes 30 hours for

One PDD and five depth profiles for 15 field sizes for each of five beam

modifiers (one open and four physical wedges) for a dual energy

accelerator

1.5 week for photon beam scanning

Equipment setup, change in machine parameters, machine faults, …

1 week for point dose collection

1-2 weeks for electron beams

1-2 weeks analysis and report writing

4-6 weeks for commissioning (excluding acceptance)