Estimated Time for Commissioning
•
It takes 30 hours for
•
One PDD and five depth profiles for 15 field sizes for each of five beam
modifiers (one open and four physical wedges) for a dual energy
accelerator
•
1.5 week for photon beam scanning
•
Equipment setup, change in machine parameters, machine faults, …
•
1 week for point dose collection
•
1-2 weeks for electron beams
•
1-2 weeks analysis and report writing
4-6 weeks for commissioning (excluding acceptance)