Southern Corridor GRIP 2017–2026
Image courtesy of FGSZ
AGRI project (TRA-N- 376)
this project consists in the installation of natural gas liquefaction facilities on the
Georgian shore and the transportation of LNG from Georgia to Romania. The Maxi-
mum Annual Capacity would be 8.0 bcma and the Maximum send-out rate
22.0mcm/d. The onshore storage capacity would be 160,000m³ and the supply
chain would be operated by two LNG carriers of 140,000m³ each.
White Stream (TRA-N-053)
This is a PCI project that consists of the implementation of an offshore pipeline in
the Black sea from Georgia to Romania. In addition to being technically challenging
(as the pipeline should cross the Black see in its longer direction) and relying on the
permission by states with contrary interests (Russia or Turkey), the project did not
show any activity in the last years.