Table of Contents Table of Contents
Previous Page  239 / 386 Next Page
Information
Show Menu
Previous Page 239 / 386 Next Page
Page Background

20.2 Notes to the consolidated financial statements for the year ended December 31, 2016

FINANCIAL INFORMATION CONCERNING ASSETS,

FINANCIAL POSITION AND FINANCIAL PERFORMANCE

20

The graduation cessation of these operations is in progress but will be fully effective

only after AREVA has fulfilled its remaining contractual commitments. These

concern the Green Innovation Project (GIFT) in the Philippines and the Commentry

Bio Energy Project (BEC) in France. Following the announcement of this cessation

of operations, various claims were lodged against the Brazilian entity. The provisions

set aside for commercial disputes and litigation in progress were reassessed, and

adjustments were made at December 31, 2016.

Adwen

Since Adwen could find itself exposed to the consequences of projects that have

been or are being executed, AREVA agreed to provide it with certain guarantees in

this regard in the agreement creating the Adwen joint venture signed inMarch 2015.

AREVA andGamesa, the two shareholders of Adwen, wished to further develop their

relationship by signing an amendment to the shareholders’ agreement of the Adwen

joint venture on June 17, 2016. At the end of a three-month competitive bidding

process designed to solicit and assess offers from potential third-party investors,

on September 14, 2016 AREVA exercised its option to sell its 50% interest in the

Adwen joint venture to Gamesa. This sale was completed on January 5, 2017, and

Gamesa holds 100% of the shares of Adwen since that date.

However, at December 31, 2016, AREVA’s obligations had not yet changed and

continued to be governed by the joint venture agreements:

p

these are first and foremost guarantees related to the past: deterioration of profit

margins as from the creation of the joint venture on projects in progress to supply

turbines to Global Tech I and Borkum West II. This guarantee is not capped;

p

other guarantees concern disputes, legal actions and claims related to operations

prior to closing but with no connection to projects in progress. That guarantee

is capped;

p

for future transactions or transactions in progress at the closing date, AREVA

will compensate the joint venture for potential losses linked to the maintenance

contracts for the Alpha Ventus, Global Tech I and BorkumWest II wind farms as

well as for the Wikinger project. Those guarantees are capped.

A dispute withGlobal Tech I began on June 1, 2016 at the latter’s initiative. It is asking

for 157million euros in late charges and repayments of excess costs concerning the

commissioning of the turbines in 2014-2015. The dispute was lodgedwith a Dispute

Adjudication Board (DAB). The DAB’s decision was published on October 22, 2016;

it orders Adwen to pay 80 million euros (excluding interest) to its customer. Neither

party wished to contest this decision by initiating an arbitration proceeding.

In addition, the final acceptance of 43 of the 80 turbines of Global Tech I was

pronounced in 2016. While the discussions with the customer continue for the

remaining 37 turbines, the latter drew on the 37 performance bonds related to

those turbines in the amount of 38 million euros, wanting to temporarily mobilize

that amount until a solution is found between the parties for the acceptance of the

corresponding turbines and in anticipation of the payment of the DAB’s decision.

All of the GTI and BWII turbines are covered by machine guarantees and are the

subject of maintenance contracts.

OPERATIONS HELD FOR SALE

(in millions of euros)

December 31,

2015 Charges

Reversal

(when

risk has

materialized)

Reversal

(when risk

has not

materialized)

Operations

held for

sale

Other

changes (*)

December 31,

2016

Operations held for sale in 2015

New NP

594

192

(152)

(3)

-

28

658

AREVA TA

154

0

(20)

(1)

-

(2)

130

Nuclear Measurements

6

4

(2)

(0)

-

(8)

-

Sub-total

753

196

(174)

(4)

-

18

788

Operations held for sale in 2016

NewCo

-

-

-

-

2,006

-

2,006

TOTAL (**)

753

196

(174)

(4)

2,006

18

2,794

(*) Including unwinding of 3 million euros at December 31, 2016.

(**) see note 3.

Provisions for cleanup

At December 31, 2016, since the “Prisme” operations prior to the final shutdown of

Eurodif’s Georges Besse I plant have been completed, all of the remaining provisions

at December 31, 2015 (11 million euros) were reversed.

Provisions for restructuring and redundancy plans

Provisions for restructuring and redundancy plans represent the best estimate of

the costs to be effectively borne in connection with workforce adjustment plans

constituting the social component of the group’s competitiveness plan. They

correspond to the different components of these plans, including in particular age-

related measures (early retirement), attrition, and the tax for revitalization of labor

pools in France. In accordance with the accounting rules, no provision was set up

for the costs of internal mobility.

For the plans undertaken in France, 2,046 departures were recorded with regard

to support measures under the Voluntary Departure Plans (VDP) in addition to 996

departures by natural attrition or in connection with contractual plans for which

provisions had already been set aside. The employee departures will be spread

out until the end of 2019.

Provisions for losses at completion

Purchase contract for separative work units (SWU) (NewCo)

In light of persistently stagnant enrichment market prices, a provision in the amount

of 50 million euros was constituted at December 31, 2015 for a SWU purchase

contract, since firm commitments on sales prices made under this contract do

not appear to be matched by the market price outlook for the period in question.

2016 AREVA

REFERENCE DOCUMENT

239