Previous Page  38 / 64 Next Page
Information
Show Menu
Previous Page 38 / 64 Next Page
Page Background

CONSTRUCTION WORLD

MARCH

2017

36

PROJECT PROFILE

• Where possible 60% of all reinforcing steel and steel products

should have a high-recycled content.

• The building will have post tensioned concrete slabs, as opposed

to conventionally reinforced concrete slabs. Post tensioned slabs

are substantially thinner and have less reinforcing steel in them

than conventional RC slabs. This not only reduces the material

used in the slabs but also reduces the size of the columns,

foundations and the concrete core walls. This will reduce the

amount of concrete and reinforcing steel used in the project by

more than 10%.

• The same principle applies in reducing the size of the core wall

through parametric optimisation.

Façade

Performance glass is used to minimise the mechanical plant

requirements and reduce operational costs.

Infrastructure and wet services

• Rainwater harvesting is future enabled. Rainwater will be drained

from the building roof using a Pluvia type system. The downpipes

will run vertically in the core and connect in a network in the

basement levels to storage tanks that could be filtered and used to

supplement the supply of water for flushing of toilets and urinals

in future.

• A sump in the lowest basement level collects ground water

seepage through the retaining walls and is pumped out by means

of a submersible type pump to irrigate the PwC gardens and the

neighbouring park. This water would have otherwise connected

directly to the storm water system and been lost.

• All excavated material has been locally reused on the rest of the

Waterfall City site.

Quantifiable time, cost and quality

Optimisation and collaboration

The tower has complex geometry and various options have been

reviewed, with the help of parametric modelling, to identify the most

efficient way of supporting the structure that complies with the

architectural intent. “Close alignment with the façade design has

allowed a seemingly difficult form to be achieved with a reasonable

degree of repetition and coordinated detailing. Buildability and

maintainability have also influenced the structural and façade

design,” adds le Roux.

Construction programme reduction

Programme reduction was taken into account when completing the

design of the project. To reduce lead time before breaking ground

on site, Arup issued earthworks as a separate package ahead

of the rest of the building. For a tall building the programme is

governed by the floor to floor cycle time. Slip forming the core adds

an early activity to the programme but then allows each floor to

be completed more quickly, saving time overall. The use of bonded

PT slabs also allowed the floor cycle time to be reduced without

compromising the future flexibility of the building.

Façade

The curtain wall is constructed using the unitised principle in which

complete glazed panels are made in a factory and then installed

onto pre-set brackets on the building. This means that:

• No scaffolding is required, which would have been very costly for

the almost 100 m height and 20 m overhang of the top floor over

the ground floor.

• Curtain wall installation can proceed before all concrete floors

are cast

• Quality is better controlled in a factory than on site.

• Panels can be installed quickly, typically 20-30 panels per day.

• Panels are watertight as soon as they are interlocked in position,

allowing following trades to commence immediately.

Risk management

Concentrated solar reflections

Le Roux comments: “The PwC façade is concave and twisting.

Considering several high profile cases beset with concentrated solar

reflection problems (notably those at 20 Fenchurch Street in London

– the ‘Walkie-Talkie’ – where plastic fittings on a Jaguar on the

street melted in 2013), concentrated solar reflections were identified

as a risk for the tower and needed careful study. At the time of

design, no general analytical software existed for calculating the

intensities of solar reflections. A purpose-built script was developed

for this analysis, with the results benchmarked against other Arup

studies globally.”

Using this script, Arup was able to calculate the magnitude of the

solar concentrations in the open areas surrounding the tower and

provide feasible and practical solutions to mitigate the impact of

the solar reflections. Solutions considered were sunshades on the