March 2016

Roofing, Ceilings, Insulation and Cladding

W

ith a proven track record,

quality products, perfor-

mance and delivery, the

company has an extensive supply

network throughout the region.

JubileeMall is located inHamman-

skraal, 30km north of Pretoria and is

a state of the art mall, which covers

52 000 m² and accommodates over

100 retail and speciality stores.

Giant Engineering specified

MiTek’s Ultra-Span roofing system.

The project required 350 trusses

and 4 600 m² of the MiTek Ultra Span

system. The initial plan was to erect

the roofing system in four weeks but

Giant Engineering completed the

project in just 14 days, which enabled

the company to save almost 50% on

labour costs.

Architect Dirk du Preez of Grace-

land Architects was taskedwith over-

seeing construction of the Mediclinic

in Kimberly. The project required

10 800 m² roofing structure and clear

spans of 25mwere specified. Roofing

specialist and MiTek licensed truss

Leading roof truss system

supplier, MiTek, has provided

r oo f i n g s y s t ems on a

number of flagship projects

throughout South Africa and

neighbouring countries.

supplier, Central Roof Industries,

installed large shallow pitched Ultra-

Span roof trusses. Timber trusses

were obviously not considered due

to the large spans and the fact that

the roof had to be made of non-

combustible materials.

Trusses were assembled on site

into braced pairs and hoisted into po-

sition on the building in accordance

with a strict time-line of the various

buildings being completed for roof

erection. Each installed roof section

then had special purlin raiser blocks

fitted (to allow for the required thick

roof insulation) in conjunction with

the support wires for the insulation

blanket. This was followed by the

fitment of the LGS purlins into the

raiser blocks before the fitment of

the roof covering of Klip-Lok sheeting.

This method ensured that the roof

sections were in fact fully completed

in appropriate portions and were

accordinglyalso inspectedandsigned

off by MiTek.All the required services

inside the roof void (which included in

some instances the support of medi-

cal equipment) were easily installed

and accommodated. This required

some site alterations but it was easily

and quickly accomplished.

Both the architect and project en-

gineer were impressed by the speed

of completion as well as with the

overall neatness of the roof structure.

The entire 10 800m² roof structure

with a mass of 125 tons of LGS plus

sheeting and insulation was com-

pleted in approximately 14 weeks.

The speed of erection ensured a total

saving of 16% compared to utilising

a hot-rolled steel structure. The roof-

ing structure cost R4,5 million of the

R220 million project.

For further information con-

tact MiTek on 011 237 8700 or

go to

www.mitek.co.za

Flagship

projects