T
he two Terex tower cranes spent
about twelve months in view of the
world-famous St. Pauli Landungs-
brücken Piers in Hamburg while working
under unique conditions. “Projects in urban
downtown settings are always associated
with special challenges, and that’s espe-
cially the case when it comes to a big, live-
ly city like Hamburg,” explains Proschwitz
GmbH General Manager Detlev Proschwitz.
The first challenge was the lack of space
around the areas where the two Terex tower
cranes would be erected. Just getting the
cranes from Proschwitz’s headquarters in
Trittau to the work site with 13 trucks was a
small logistical challenge despite the short
distance of 35 km – after all, cramped
downtown areas are hardly the natural hab-
itat of heavy goods vehicles. Despite this
and the limited space conditions at the ac-
tual work sites, the Proschwitz team was
able to erect the two cranes on time, with
each one taking only one day and three
assembly technicians. “We didn’t have any
more time available anyway, as we had
to keep the necessary road closures to a
minimum. That’s where the CTT cranes’
ease of erecting really came through for
us,” Proschwitz emphasizes. And it is one
of the key reasons why his company con-
sistently relies on Terex products when it
comes to tower cranes: The Proschwitz
Group’s rental fleet features a total of over
100 flat top and hammerhead tower cranes
– all Terex models. “The feature with the
transfer masts that work on both model
ranges enables us to use a variety of com-
binations and tackle all kinds of challenges
in a flexible and cost-effective manner,”
Proschwitz says. He mentions Terex's com-
petitive prices, and the fact that experience
has shown that they keep their value well,
as additional points in their favour.
The two Terex tower cranes have another
feature that make it seem as though the
units were destined to work on the project at
the Hamburg site – their variable frequency
drives, which guarantee low inrush currents,
protecting the city grid from unmanageable
voltage fluctuations. “If there was one thing
we really didn’t want to do, it was to leave
the Landungsbrücken Piers without electric-
ity,” says Detlev Proschwitz.
For the project at the St. Pauli Landungs-
brücken Piers, the Proschwitz team erect-
ed the CTT 91-5 flat top tower crane
free-standing on a C38 cruciform base,
and the CTT 161A-8 flat top tower crane on
cast-in-place anchors. With a jib length of
40 m and a hook height of 49.5 m, the CTT
161A-8 was perfectly set up to lift construc-
tion materials weighing up to 4.15 tonnes
from the jib tip. Its maximum lifting capacity
was eight tonnes. The CTT 91-5 was set up
with a jib length of 30 m and a hook height
of 40.8 m. With this setup, it was able to
pick up loads of up to 3.3 tonnes.
With these configurations, the two Terex
tower cranes performed their work smooth-
ly and reliably for a total of twelve months,
even when exposed to wind and inclement
weather. As a result, Construction Manager
Robert Friske from Köster AG, the primary
contractor on the project, was also com-
pletely satisfied with the Terex machines:
“The high-pressure deadlines normally in-
volved in this type of construction projects
mean that we can’t afford any equipment
downtimes. This means that dependable
machinery, such as these two tower cranes,
is crucial to a successful project completed
on time,” Robert Friske pointed out.
After the work was completed, the cranes
needed to be disassembled quickly, as both
the port’s anniversary celebration and the
Hamburg Marathon were just around the
corner. Due to the extremely constrained
space conditions, it was not possible to
tear down the CTT 91 crane using a mo-
bile crane. However, the fact that the tower
crane can be easily dismantled into smaller
components meant that the CTT 161 crane
was able to take care of the task and safe-
ly disassemble its 'smaller sibling.' “The
option of being able to disassemble the
slewing unit came in really handy,” explains
Proschwitz. “There’s no other machine with
that available!”
After the CTT 91 was dismantled, the CTT
161 was disassembled in six hours with the
help of a mobile crane.
b
TEREX
®
TOWER CRANES
working at the St. Pauli Landungsbrücken Piers in Hamburg
LIFTING
CAPITAL EQUIPMENT NEWS
NOVEMBER 2015
19




