MINING News

The bulk sampling plant at Montepuez has been fully commissioned (photo: Mustang).

the Mustang concession boundaries.

“The September quarter was a highly

productive period for Mustang at both

a corporate and operational level, high-

lighted by the commencement of our bulk

sampling at the Montepuez ruby project in

Mozambique,” comments Mustang’s MD,

Christiaan Jordaan.“As reported post quar-

ter end, the company was very pleased to

recover 460,43 carats of high quality rubies

from our bulk sampling start-up phase,

with recoveries anticipated to increase in

the comingmonths as production is scaled

up to circa 350 m

3

per day.

“During a site visit in July 2016, Mr

Vincent Pardieu, an independent gemolo-

gist with the GIA (Gemological Institute of

America), confirmed Mustang’s rubies are

high-quality and equivalent to other sec-

ondary deposits mined in the region – a

very important distinguishing factor of the

Alpha deposit.”

Mustang also holds interests in the Save

Birimian concludes agreement with Morila

ASX-listed Birimian Limited says it has

entered into an agreement with Société des

Mines de Morila (Morila) that could lead to

the commercialisation of several of its gold

deposits within its Massigui gold project in

Southern Mali.

According to Birimian, this agreement

provides a potential low risk, low cost pro-

cessing solution for these deposits, whilst

the company retains the significant upside

potential for further gold discoveries in the

broader project area.

Under the terms of the agreement,

Morila has been granted a six-month option

to acquire an ‘Area of Interest’ within the

project.

The Massigui gold project surrounds the

Morila mine lease on three sides and covers

strike extensions of the highly prospective

geological sequence that hosts the 7 Moz

Morila gold deposit.

Birimian has made significant gold dis-

coveries at three prospects, namely Ntiola,

Viper and Koting. These prospects are

situated in close proximity to the under-

utilised 4 Mt/a Morila treatment plant. Over

35 000 m of drilling has been completed on

the project to date.

River diamond and Balama graphite proj-

ects, also in Mozambique, but Montepuez

ranks at its flagship.