Previous Page  35 / 56 Next Page
Information
Show Menu
Previous Page 35 / 56 Next Page
Page Background

DIAMONDS

November 2016

MODERN MINING

33

State of-the-art plant under construction

The C-Cut project is not the only

major capital investment in prog-

ress at Cullinan. Petra Diamonds is

also in the process of replacing the

present sprawling treatment plant,

originally commissioned in 1947,

with a state-of-the-art processing

facility, which will have a compact

footprint, a high degree of energy

efficiency and feature modern

technologies – such as autogenous

milling – designed to increase dia-

mond liberation and minimise

breakage of the large gem-qual-

ity stones for which Cullinan is

celebrated.

The plant, which will deliver

a R20 to R25 saving per tonne in

processing costs, is expected to

be fully operational by the end of

Petra’s 2017 financial year. The

capex for the project is R1,65 bil-

lion with payback anticipated in

just three years.

advanced stage. The company also facilitated

the engineering for the Koepe winder upgrades.

The two winder upgrades were completed in

December 2014 and December 2015 respec-

tively, taking advantage of the holiday breaks

so as to minimise disruption to operations.

Murray & Roberts Cementation deployed

around 380 people on its contract at peak but

this has now reduced to about 60 people as the

contract draws to a close. Says Duyts: “This

has been a very successful contract from our

point of view and we’re very proud of the fact

that we’ve managed to meet all key dates and

maintain a safety record that is ahead of indus-

try norms. Factors contributing to our success

have included the excellent relationship we

developed with the Petra team and the inten-

sive planning we put into every stage of the

work. It also goes without saying that you need

to have the right people on the job and this was

certainly the case here.”

Commenting on the overall state of progress

on the C-Cut project, Cloete says the project is

running within schedule and budget. “The first

undercut rings were drilled and blasted during

June 2015 and the first draw bell drilled and

blasted during January this year,” he states. “In

terms of waste and blue (kimberlite) develop-

ment, we’ve completed approximately 22 km of

the nearly 27 km required. Of the total capital

budget of R4,2 billion, around R3,4 billion has

Draw point on the extrac-

tion level.

been spent – which is over 80 %. The first ore

from the C-Cut was delivered a year ago and

we’re expecting the project to contribute 1 Mt

of the total ROM production of 2,8 Mt planned

for our 2017 financial year, which runs to

30 June 2017.

“Full production will be achieved in

FY2019, by which time carat production will

have increased from 0,68 Mct/a currently to

around 2,2 Mct/a, with all of this – other than

about 200 000 carats from the reprocessing of

tailings dumps and around 120 000 carats from

the upper levels – being derived from C-Cut

ore. The project is transformational for Cullinan

and will ensure that the mine remains Petra’s

flagship for many years to come.”